159-Acre Logistics Yard With 3,416 Parking Spaces Proposed for Google Data Center Construction

Plans for a 159-acre temporary logistics yard in Columbia County include a 3,416-space parking lot to support construction of the White Oak data center, according to a filing with the Georgia Department of Community Affairs.

The proposal, which covers the site at 870 Progress Drive, is intended to serve as a staging area and office space for the massive infrastructure project. By comparison, the Columbia County Fairgrounds currently provides parking for approximately 1,000 vehicles.

Logistics Yard Development Timeline

Milestone Date
Data center approval by county commissioners Feb. 3, 2026
Logistics yard filing date Nov. 16, 2026
Filing status updated to “warrants regional review” Nov. 18, 2026
Logistics yard completion estimate September 2027
Overall data center project completion estimate September 2035

Turner Construction is developing the site on behalf of Kinetic Infrastructure Solutions, an affiliate of Google. The filing estimates the logistics yard will create roughly 400 full-time jobs during the construction phase and reach a value of $50 million upon build-out.

Traffic management plans include a new curb cut for US 221/Appling Harlem Road, with additional corridor upgrades currently awaiting review by the Georgia Department of Transportation. The project is expected to generate 1,596 peak-hour vehicle trips.

Photo: yahoo.com

In a Nov. 11 letter, the Southern Environmental Law Center and the Savannah Riverkeeper urged the U.S. Army Corps of Engineers to reject a federal wetlands permit, citing potential permanent impacts to over 24,000 linear feet of streams and 4.36 acres of wetlands.

County Plans Tax Relief Using Data Center Revenue

County Manager Scott Johnson said Columbia County intends to use excess revenue from the Google data center project to cover property taxes for homeowners with a homestead exemption. Google has signed a $280 million agreement with the county spanning the seven-year construction period, Johnson said.

Permit Application Details Temporary Laydown Yard

The mass grading project would include temporary staging areas, the proposed 3,416-space parking lot and an office for construction, according to the county’s Developments of Regional Impact statement.

The regional commission has yet to release its findings regarding the logistics yard proposal, and the status of the required federal environmental permits remains unresolved.