The Alaska Energy Authority on Tuesday approved a $4.9 million loan to build a solar farm at the Red Dog Mine, 105 miles north of the Arctic Circle, with the 8.8-megawatt array and 15-megawatt-hour battery expected online in October 2028.
The AEA board voted unanimously to lend the money through its Power Project Fund to Tugliq RedDog1, a subsidiary of a Canadian energy company that will build, own and operate the roughly $35 million project and sell the electricity to mine operator Teck Alaska. Site work began in June, according to the state’s loan review, Electrek reported.
| Metric | Current mine | With solar + storage | Post-closure (cleanup only) |
|---|---|---|---|
| Diesel burned | ~40,000 gallons/day | Displaced by solar output | Minimal |
| Power demand | ~25 MW average | Solar covers ~5% | Solar covers ~90% |
Thayer calls project a renewable-mining balance
Thayer called the project a balance of renewables supporting mining and said that it displaces diesel, which he described as very expensive.
Thayer also said he thinks this is the first time the Power Project Fund has lent money to support a mine.
Project scale and timeline confirmed in state plans
Plans filed with the state call for more than 15,000 panels across about 30 acres, an area roughly the size of 23 football fields.
Site work began in June, according to the state’s loan review, and the solar and storage system is expected to come online in October 2028.
The Red Dog Mine is the world’s largest producer of zinc, accounting for 10% of global zinc production and holding the world’s largest zinc reserves, per Wikipedia. The facility operates on land owned by NANA Regional Corporation, an Iñupiat-owned Alaska Native corporation created under the 1971 Alaska Native Claims Settlement Act, and is operated by Teck Resources through its subsidiary Teck Alaska.

The mine sits on land owned by NANA, an Iñupiat-owned Alaska Native corporation. All of its power today comes from on-site diesel generators fed by fuel barged to a port near Kivalina and trucked 52 miles to the site. The eight generators burn nearly 15 million gallons a year, and summer demand can run high enough that Teck has to cut power elsewhere at the site, Alaska Public Media reported.
AEA Executive Director Curtis Thayer said the loan carries a 5.5% interest rate against a market rate of about 6.6%, and the agency is confident it will be repaid even if the mine closes on schedule in 2031. “It’s nice to have renewables supporting a mining activity. It’s a balance,” Thayer told Alaska Public Media. “The one thing is it displaces diesel, and diesel is very expensive.”
Teck has pursued renewable power at Red Dog for years, installing a weather tower in 2024 to evaluate wind potential and first proposing the solar farm in March. The company is also studying whether to develop two nearby deposits; if that expansion proceeds, the state projects the solar and battery system would cover about 3% of the larger operation’s electricity needs, according to the loan review cited by Electrek.
If mining ends, demand will drop sharply but the site will still need electricity for long-term water treatment and cleanup. Thayer said the solar farm would then supply about 90% of the site’s annual power needs.
“There’s remediation that has to be done once the mine is closed, and so this will pay for that,” he said.
Teck and Tugliq did not immediately respond to requests for comment, Alaska Public Media reported.