The Alaska Railroad’s long-dormant 32-mile spur to Port MacKenzie has secured a $249 million federal grant, reviving a project first conceived in 1992 before the port itself existed.
The railroad’s board approved the $311 million project this past week, and Chief Executive Bill O’Leary told the Alaska Beacon that construction could begin next summer. A state transportation department briefing says the state has already invested $184 million in rail infrastructure.
While the line is publicly pitched as a freight corridor for minerals, natural gas pipeline materials and national security, land-use records at both termini show plans for large-scale data centers powered by a proposed coal plant. At Port MacKenzie, Terra Energy Center Corp. holds a permit for roughly 1,058 acres near Lake Lorraine to test an “Advanced Manufacturing & Compute Campus” with an initial 30 MW load, according to a September 2025 Port Commission packet cited by the Alaska Beacon.
The developer would need to pour a slab by Dec. 31, 2028, or risk losing the land. The resolution lists its first priority as “Attraction of data center and advanced computing facilities.” It promises “firm baseload power supply from TECC’s planned generation facility” and says land near Port MacKenzie offers “exceptional access to tidewater.”
At the Houston end, where the spur would meet the main line, the Alaska Industrial Development and Export Authority (AIDEA) has proposed roughly 20,000 acres for secure data centers, a “behind-the-meter data park” and a data/energy campus linked by utility corridors, Urgent reports.
The state Department of Natural Resources recently approved a smaller transfer of about 6,800 acres, though borough officials have asked the state to reconsider, suggesting Point MacKenzie and West Susitna as more suitable sites. Neither data center has a committed tenant.
In March, the Interior Department announced that Terra Energy Center reached a $1 billion agreement in principle with Hyundai Heavy Industries Power Systems for boilers for a 1.25-gigawatt coal plant — what the department called “the first order of utility-scale coal power plant boilers in the United States since approximately 2006.” Korean private equity firm KOREIT pledged $500 million.
The Matanuska-Susitna Borough Assembly voted in March to jointly market the port with Terra to attract “large power consumers,” prioritizing “data center and advanced computing facilities” and promising “firm baseload power supply from TECC’s planned generation facility.” The resolution and an attached staff memo do not use the word coal; the Interior Department’s announcement does.

Mayor Edna DeVries vetoed the resolution March 5, citing “the risk that Mat-Su Borough has placed themselves in” and noting that data centers “often require conditional use permits,” a subject “the assembly has not discussed.” The Assembly overrode her 6-1 on March 17, the Anchorage Daily News reported. The resolution does not obligate the borough to sell or lease land.
Lawmakers back port marketing with data centers as top priority
House Joint Resolution 14 cleared its final vote in April, with lawmakers approving it 58-1, according to a state transportation department briefing.
The resolution does not obligate the borough to sell or lease land.
State trims Houston land transfer amid borough objections
AIDEA’s application called the site a behind-the-meter data park, but the authority has not committed to any specific tenant.
The Department of Natural Resources cited public concerns, including the prospect of scalable data center facilities, in its decision to approve the reduced acreage.
The Alaska Railroad’s board approved the $311 million Port MacKenzie spur project this past week after the U.S. Department of Transportation awarded a $249 million grant, covering roughly 80 percent of the total cost.
The railroad’s own page notes that in 2019 it generated a US$21.6 million profit on revenues of US$203.9 million while holding US$1.1 billion in total assets, illustrating a modest operating margin that makes a project of this scale dependent on external capital. Since state ownership began on January 6, 1985, major capital investments have routinely relied on federal appropriations rather than retained earnings.
The U.S. Department of Transportation’s grant announcement does not mention data centers or coal, focusing instead on moving Alaska’s mineral and energy resources. Meanwhile, incoming Gov. Jonathan Kreiss-Tomkins, a Democrat, has said he would seek a temporary ban on new data centers.