Augusta Pauses Data Center Applications After $2 Billion Project Reveals Oversight Gaps

Augusta, Georgia, imposed a temporary halt on new data center applications on June 2, 2026, citing concerns over public oversight in major developments.

The decision followed the advancement of Project Eisenhower, a $2 billion data center campus developed by QTS Data Centers.

The 200-acre QTS campus along Gordon Highway received its initial zoning approval in 2022 and subsequent expansions in 2024 and 2025. Preliminary site work began in 2026, though additional municipal approvals are required for future construction phases. The project includes six buildings, with the first facility expected for completion in spring 2028.

Zakiya Mabery, a homeowner in the Haynes Station neighborhood, questioned whether residents received sufficient opportunities to participate in decisions about a computing facility located about a 10-minute walk from her home. Black residents represent approximately 67% of the community closest to the proposed site.

Augusta commissioners approve temporary moratorium on data centers — WJBF

In response to community feedback, the Augusta Commission unanimously approved a 60-day extension to its moratorium on July 21, 2026. On October 6, the commission adopted new data center regulations through a 6-to-5 vote. The ordinance requires 500-foot buffers between data centers and residential or agricultural properties, which can be reduced to 300 feet with qualifying landscaped barriers.

The new standards also establish noise limits of 65 decibels during the day and 60 decibels at night along neighboring property lines. Developers are restricted from using water-intensive cooling technology and private wells for cooling systems.

Research from Harvard University suggests a connection between public participation and data center approval rates. Among cases examined, communities that held public hearings successfully blocked proposed developments 66% of the time. In contrast, authorities approved 80% of projects in communities without hearings.

A separate study by researchers from George Washington University Law School and American University analyzed more than 5,200 data centers across the nation. The November 2026 research found that majority-Black neighborhoods had approximately 2.2 times the odds of hosting data centers compared with majority-white communities within the same state, after accounting for demographic, economic, and geographic factors.

Jci data centers

QTS plans to use closed-loop cooling technology at its Augusta campus. The company estimates a standard building requires about 600,000 gallons for the initial system fill, with an additional 50,000 gallons consumed monthly for other facility needs. Augusta Utilities has issued a will-serve letter, though actual usage will depend on final designs.

The Georgia Environmental Protection Division is reviewing a draft air quality permit for the QTS facility, which covers emergency diesel generators. A public meeting and hearing are scheduled for December 3, 2026, from 6 p.m. to 7:30 p.m., with written comments due by 4:30 p.m. that day.

Augusta puts a hold on data centers — except the one that’s riled up neighbors — WRDW News 12

Georgia’s governor-elect, Keisha Lance Bottoms, has announced plans to issue an executive order pausing new data center development, though the duration remains undetermined. The state’s next legislative session is set to begin on January 11, 2027.