Voters rejected a data-center rezoning in August, yet Augusta Township still lacks a moratorium or final regulations for the facilities.
A special Planning Commission meeting set for Nov. 23 to discuss a six-month pause was canceled because officials could not secure a location, The Sun Times News reported.
Frustration boiled over at the Nov. 24 Board of Trustees meeting. One commenter asked whether the commission could meet weekly instead of monthly to finish the rules. “The current ordinances can’t account for a facility of that type that could come in,” he said. Supervisor Todd Waller insisted he personally opposed data centers but said his views could not override the law. As the exchange continued, Waller told an audience member, “I’m not going to argue with an idiot.”
The Aug. 4 referendum defeated the rezoning of more than 500 acres near Milan by a 2,314-to-269 margin. The board’s 2025 rezoning votes also triggered recall efforts against all seven elected township officials; 14 petitions cleared county review in September.
Records show the Planning Commission has discussed data-center regulations since at least March. In June, commissioners recommended an ordinance creating a process for a temporary development pause.
By July 15 they were reviewing permanent standards for facilities that heavily tax infrastructure. The township board adopted the process ordinance Sept. 22 on a 6-1 vote, with Waller casting the lone dissent. That ordinance established a procedure but did not enact a pause; commissioners must now document the need for one before recommending it to the board.
The next regular Planning Commission meeting is scheduled for Dec. 16. The Nov. 24 board packet also lists a $6,000 escrow refund to Thor Equities, the developer behind the earlier rezoning, as an outstanding payment.
Whether the company intends to pursue future development in Augusta remains unclear.
Meanwhile, Washtenaw County released the second phase of its municipal data-center planning toolkit in November, offering guidance on temporary pauses, zoning, operating standards and community-benefit agreements.
New research from the Citizens Research Council of Michigan warns that rising electricity demand from data centers could jeopardize Michigan’s 60% renewable-energy target for 2035, noting DTE Energy will need additional renewable sources beyond previous plans to serve the 1.4-gigawatt center under construction in Saline Township.
See a video of Augusta Township Supervisor Todd Waller's comments at a public hearing on a proposed moratorium on data centers. https://t.co/tghk4KQdiq pic.twitter.com/Zl8AE06Ssh
https://t.co/tghk4KQdiq
See township leader caution against deterring data center development https://t.co/IpdeA1FJWJ