Indonesia’s nuclear regulator has approved the first step for a planned 250 megawatt nuclear power plant in Bangka, completing the review ahead of schedule, Tempo.co reported.
Bapeten granted site evaluation approval to PLN Nusantara Power for a proposed plant in Teluk Menggris, West Bangka. The approval, received on Friday allows the company to begin detailed field investigations at the site.
- Bapeten approved site evaluation for a 250 MWe nuclear plant in Teluk Menggris.
- The review took four months and 18 working days, ahead of the standard six-month timeline.
- The approval is not a permit for physical construction, but a prerequisite for further study.
- The project will use an advanced Small Modular Reactor (SMR) technology.
The approval followed a technical review of documents submitted on July 8, 2026, and on-site verification by the Nuclear Energy Regulatory Agency, as noted by tech.aseancoverage.com.
Wiryono, Bapeten’s Director of Licensing for Nuclear Installations and Materials, stressed that the approval does not permit physical construction. This is a mandatory prerequisite step that must be completed before the company can carry out a more thorough evaluation of the location.
“The site evaluation approval does not constitute a permit to begin physical construction of the PLTN,” he said, as quoted from a written statement on Friday, November 27, 2026.
Abdul Qohhar, Bapeten Public Relations Coordinator, explained that the approval confirms the Site Evaluation Program and Management System documents meet safety standards.
The site evaluation will examine six safety factors: seismicity, geotechnical and foundation conditions, volcanology, hydrology and meteorology, human-induced events, and radioactive material dispersion.
Bapeten said that licensing for the plant proceeds in stages under Government Regulation No. 28 of 2025 and Bapeten Regulation No. 5 of 2025.
For reactors above 10 MWe up to 300 MWe, the stages include site evaluation approval, site approval, design approval, construction permit, commissioning approval, operating permit, and decommissioning approval.
Bapeten’s Head of the Legal, Cooperation, and Public Communication Bureau, Ishak, reiterated that safety and security are paramount principles throughout the plant’s development.
The agency also affirmed its commitment to transparency and regulatory independence. Updates on the plant’s oversight are available through the PLTN Supervision Corner menu on Bapeten’s official website.