BART Yellow Line Faces 15-Minute Delays for Six Nights of Fiber Work Starting Nov. 30

Expected delays of 10 to 15 minutes will hit the San Francisco Bay Area Rapid Transit District Yellow Line after midnight on six nights starting Nov. 30, 2026, due to single tracking between North Concord/Martinez and Pittsburg/Bay Point, Railway Supply reported.

Crews will install new fiber optic cable on this Contra Costa County stretch. The agency’s late-night work notice lists the active dates as Nov. 30, Dec. 2 and Dec. 8 through 11.

Each shift starts shortly before midnight and wraps up before regular service resumes the next morning. Trains will share a single track through the active zones during these windows.

From midnight onward, riders should anticipate the 10 to 15 minute setbacks. The agency notes that the work may slightly delay the evening’s final train transfers, though every passenger will still reach their destination.

The Grand Meet at MacArthur and the last transfer to the Antioch diesel multiple unit train will be coordinated. All six work dates fall on weekdays, when operations run from 5 a.m. to midnight.

Last Weekday Eastbound Yellow Line Trains from SFO
Departs SFO MacArthur North Concord/Martinez Pittsburg/Bay Point Antioch
11:08 p.m. 11:58 p.m. 12:27 a.m. 12:34 a.m. 12:53 a.m.
11:28 p.m. 12:18 a.m. 12:47 a.m. 12:54 a.m. 1:13 a.m.
11:50 p.m. 12:39 a.m. 1:09 a.m. 1:15 a.m. Ends at Pittsburg/Bay Point
11:59 p.m. 12:52 a.m. 1:21 a.m. 1:28 a.m. 1:43 a.m.

These times derive from BART’s Aug. 10, 2026, weekday Yellow Line timetable, showing normal schedules without work disruptions. On a regular weekday, the last four eastbound departures from SFO reach North Concord/Martinez between 12:27 a.m. and 1:21 a.m.

Three of those late trains continue onward to Antioch, while the 11:50 p.m. departure terminates at Pittsburg/Bay Point. The timetable identifies the 11:59 p.m. departure from SFO as the final train of the evening serving all stations.

The cable installation supports dedicated communications infrastructure under the agency’s Digital Railway modernization effort. Officials state the added fiber provides critical redundancy and extra pathways for traffic, protecting network operations against disruptions.

Earlier phases placed work between Walnut Creek and Pleasant Hill stations in September, before shifting to the North Concord/Martinez and Pittsburg/Bay Point segment in October. BART’s October 2026 ridership snapshot recorded average weekday totals of 817 at North Concord/Martinez and 2,843 at Pittsburg/Bay Point.