Belgian Authorities Order Google to Halt AI Data Centre Construction Over Revoked Permit

Belgian authorities ordered Google to halt construction of a large AI data centre near Charleroi on Thursday after inspectors found a three-hectare building nearly complete despite the revocation of its amended planning permit in August. The Walloon regional government said it had referred the matter to prosecutors, alleging a major offence, and Google confirmed it had paused work pending additional guidance.

Inspectors visited the Écopole business park in Aiseau-Presles on November 26 and discovered the structural shell of a 30,000-square-metre building closed and almost finished, Walloon official Raphaël Stokis told public broadcaster RTBF, according to The Guardian.

About 300 workers received a verbal stop-work order that was confirmed in writing to Google, Stokis said. Nicolas Yernaux, a spokesperson for the Walloon administration, told Agence France-Presse on Friday that a report alleging “illegal construction of a building covering 3 hectares” was being submitted to the public prosecutor’s office, Le Temps reported.

Permit revoked over water draw

The dispute centres on changes Google sought to its original 2024 permit, which approved three smaller, air-cooled data centres on the 50-hectare former coal mine site. In 2025, the company applied to merge two buildings into one larger facility and switch to liquid cooling drawing 600 cubic metres of water per hour from the River Sambre, Data Center Dynamics reported. The Walloon administration approved the amendment in April 2026, but residents appealed.

Following an exceptionally hot and dry summer, Wallonia’s Infrastructure Minister François Desquesnes revoked the amended permit in August, citing drought concerns. He said that Google’s existing Saint-Ghislain data centre withdraws one billion litres of water annually for cooling, returning one quarter and evaporating the rest. Google appealed the revocation to Belgium’s Council of State; a hearing is scheduled for January 7, 2027, Superpower Daily reported.

Greenpeace triggered enforcement

Greenpeace Belgium published drone footage on November 23 showing construction continuing after the August revocation and filed an emergency appeal with local planning authorities.

“That Google continues to build without a permit is disrespectful to the environment, local residents, and the law,” said Joeri Thijs, spokesperson for Greenpeace Belgium, in a statement to BBC News. “The consequences of the climate crisis will only increase. In this context, the construction of energy-guzzling data centres cannot remain under the radar.”

Google belgium st ghislain ii fill
Photo: Data Center Dynamics

The environmental group said satellite imagery from five observation dates between August 13 and November 14 supported its request for an immediate halt, Unite.AI reported. Nadia Cornejo, a Greenpeace spokesperson, welcomed the reported stoppage and said the group would continue monitoring activity at the site.

Regional framework tightens rules

The Walloon government published a new framework on November 12 that identifies electricity, land and water as strategic constraints for data centre development. It bars data centres from sites meeting regional strategic-location criteria, subject to exceptions, and sets expectations for water efficiency and waste-heat recovery, according to Unite.AI.

Yernaux told RTBF that work could continue under the original 2024 permit for three smaller air-cooled centres, but not under the refused amendment. “They built the new building as if they had obtained the amended permit, but they had not,” Yernaux said.

Permit revoked over water draw

Following an exceptionally hot and dry summer, Wallonia’s Infrastructure Minister François Desquesnes revoked the amended permit in August, citing drought concerns. He said that Google’s existing Saint-Ghislain data centre withdraws one billion litres of water annually for cooling, returning one quarter and evaporating the rest. Google appealed the revocation to Belgium’s Council of State on October 17, 2026; a hearing is scheduled for January 7, 2027, Greenpeace’s account of the proceedings shows.

Belgian authorities order Google to halt data center construction after permit revocation
Photo: Superpower Daily

Greenpeace triggered enforcement

Greenpeace Belgium published drone footage on November 23 showing construction continuing after the August revocation and filed an emergency appeal with local planning authorities. “That Google continues to build without a permit is disrespectful to the environment, local residents, and the law,” said Joeri Thijs, spokesperson for Greenpeace Belgium, in a statement to BBC News.

Nadia Cornejo, a Greenpeace spokesperson, welcomed the reported stoppage and said the group would continue monitoring activity at the site.

Regional framework tightens rules

The Walloon government published a new framework on November 12 that identifies electricity, land and water as strategic constraints for data centre development. It bars data centres from sites meeting regional strategic-location criteria, subject to exceptions, and sets expectations for water efficiency and waste-heat recovery, according to Unite.AI.

Greenpeace reports construction halt at googles belgian data center
Photo: Unite.AI

Parallel investigation in Finland

The Belgian case follows another setback for Google in Europe. In October, Finnish authorities launched a criminal investigation into possible environmental violations at a Google data centre site in Muhos, where the company was accused of illegally felling some 250,000 trees, Data Center Dynamics reported. Construction there has been suspended pending completion of an environmental impact assessment.

Google said in a statement it was “committed to maintaining an open and collaborative dialogue” with regional authorities and had operated in Belgium for over 15 years. The company told BigGo Finance it acted “consistent with the direction from local authorities and pending additional guidance.”

Parallel investigation in Finland

The Belgian case follows another setback for Google in Europe. In October, Finnish authorities launched a criminal investigation into possible environmental violations at a Google data centre site in Muhos, where the company was accused of illegally felling some 250,000 trees, Data Center Dynamics reported. Construction there has been suspended pending an environmental impact assessment.

Google said in a statement it was “committed to maintaining an open and collaborative dialogue” with regional authorities and had operated in Belgium for over 15 years. The company told BigGo Finance it acted “consistent with the direction from local authorities and pending additional guidance.” A ruling on Google’s appeal of the permit revocation is expected on January 7, 2027.