Black Hills Energy Agrees to Delay Lange II Power Plant Surcharge

Black Hills Energy has agreed to delay a proposed monthly surcharge for its Lange II power plant, pausing a plan that would have added roughly $17 to $20 to residential bills starting in December.

The South Dakota Public Utilities Commission voted unanimously Thursday to defer the legal dispute over whether the utility can collect the charge on an interim basis. Under the agreement, Black Hills Energy will not seek to implement the surcharge before Feb. 1 or until the Rapid City plant begins operating, whichever is later, Mitchell Republic reported.

  • Surcharge delayed until Feb. 1 or plant startup, whichever is later
  • Would add $17.26–$19.70 monthly for typical residential customers
  • Commission staff argued state law bars interim collection
  • Legal question over interim authority remains unsettled

Rate increase already in effect

A separate rate increase approved by the commission on Nov. 5 already adds about $16 per month to the typical residential electric bill for the utility’s 75,000 customers in western South Dakota. Business customers also saw increases.

Photo: capjournal.com

Surcharge details shift

Black Hills Energy initially proposed a $19.70 monthly surcharge based on 650 kilowatt-hours of usage, then revised it to $17.26 for 600 kilowatt-hours. Commissioner Chris Nelson flagged the discrepancy at Tuesday’s hearing.

“I would encourage Black Hills to figure out what the right number is, and then communicate that so we can all be using the same number there,” Nelson said.

The surcharge would recover about $37.5 million annually toward the roughly $320 million cost of the Lange II natural-gas-fired plant in Rapid City, and would face annual commission review if approved.

Legal authority challenged

Commission staff objected to the interim request, arguing state law does not grant utilities authority to impose a surcharge before final approval. That authority is typical in general rate cases, where customers are refunded if the commission later reduces or rejects the increase.

“I think there’s a real legal question as to whether you can even do that,” Nelson said of the interim request.

“Hopefully, we don’t have to adjudicate that, but if we do at some point, well, that’s why we’re here.”

An attorney for Black Hills Energy said Thursday that a delayed startup for the Lange II plant contributed to the decision to withdraw the interim request, kotaradio.com reported.

Merger backdrop

Black Hills Energy and NorthWestern Energy recently completed a merger forming parent company Bright Horizon Energy, serving 2.2 million customers across eight states. Montana’s regulatory approval of that merger is being challenged in court. Both utilities will continue to operate and file for rates separately, Commissioner Kristie Fiegen said in a June statement.