Engineering firm Bartlett & West handed the Capital Area Metropolitan Planning Organization the final study for the US 50/54/63 interchange on Monday, mapping out ramp changes for a junction that carries more than 80,000 vehicles a day.

The CAMPO board accepted the report during its November 18 meeting, giving Jefferson City its first comprehensive look at reconfiguring the Tri-Level since the structure opened in the early 1960s, according to the city’s official release.

The study area stretches from Dix Road to Jackson Street and from Linden Drive to the Missouri River bridge, covering the full tangle of merging lanes and tight turning radii that have frustrated drivers for decades.

Bartlett & West evaluated existing traffic conditions, crash history and a menu of geometric improvements for the interchange and the adjacent Whitton Expressway corridor. The firm stopped short of endorsing a single build alternative; instead it laid out a framework for future project development, environmental review and the funding conversations that must follow. No construction money or timeline exists yet.

CAMPO Board Accepts Tri-Level Study Mapping Ramp Changes

“The completion of the study does not establish construction funding or a timeline for improvements,” the city said in its summary. “Additional coordination, project development and funding would be necessary before improvements could advance.”

MoDOT has long classified the interchange as an unfunded need. The original 1960s design left short acceleration lanes, non-standard ramp geometries and weaving sections that create daily bottlenecks and a higher-than-average crash rate.

The new study is designed to serve as the technical backbone for future grant applications, including potential submissions under MoDOT’s unfunded-needs process and federal discretionary programs. CAMPO can now point to a finished, engineer-vetted document when competing for limited state and federal dollars.

Capital Area Metropolitan Planning Organization is federally mandated for comprehensive transportation planning in the Austin, Texas, US area, serving several counties. As one of 25 Texas MPOs, it is required to produce both a 20+ year Regional Transportation Plan and a four-year Transportation Improvement Program. The RTP is adopted by the CAMPO Board every five years and must be multimodal, incorporating transit, walking, and biking alongside roads.

Project development, environmental clearance under NEPA, right-of-way acquisition and final design all sit ahead of any shovel hitting dirt. Each phase requires its own funding commitment. For now, the Tri-Level stays as it was built: a 1960s solution carrying 2020s traffic volumes, with the study sitting on the shelf until a budget catches up to the engineering.