Colorado adopted the 2024 International Plumbing Code and International Residential Code, plus selected Fuel Gas Code provisions, with state amendments now in force.
The rules reshape daily practice for plumbers, contractors and design professionals — supervision limits, permit timing, testing protocols, and how businesses identify themselves on vehicles and online.
The Board conducts compliance checks statewide, with priority on schools, hospitals and public buildings, so gaps are more likely to be caught. For emergency work — broken water or drain lines, water-heater replacement — a permit may be obtained on the next business day after work begins.
Vehicle markings must appear in at least two locations with characters at least two inches high. Contractors must update the required information within 90 days after a change.
Backflow-preventer assemblies must still be tested at installation, after repair or relocation, and at least annually by a certified cross-connection control technician. Temporary-heating installations are expressly subject to inspection and pressure testing. Where plastic vent piping serves a gas-fired water heater, the venting system must be pressure-tested before the appliance is connected.
Graywater fixtures must display a reuse warning. Systems using nonpotable-water reuse must include a reduced-pressure backflow preventer at the building service. The amendments also remove rainwater-system provisions; project teams should confirm applicable requirements with the authority having jurisdiction.
Definitions of “trap drain” and “fixture drain” are clarified to distinguish the trap arm from downstream piping. Cleanouts at the building-drain/building-sewer junction must use a two-way configuration, subject to depth and material limits, and must be installed and tested during the underground or rough-in stage.
Floor or trench drains in utility buildings and residential garages may daylight or discharge to an approved alternative disposal system only with written approval from the authority having jurisdiction, the Colorado Department of Public Health and Environment, or the applicable sewer purveyor. Service sinks and mop sinks are prohibited in toilet rooms, bathing rooms and food-preparation areas.
Violations of the Board’s rules can lead to three types of penalties. Second, the Board can go to court for an injunction. Paying a fine does not excuse correcting the underlying violation.