Columbia Gas to Replace Aging Lines in Two Bay Village Areas

Columbia Gas will replace aging gas lines in two Bay Village areas starting in January, part of a broader infrastructure upgrade across its Ohio service territory, Cleveland.com reported.

The east-end project covers Bruce Road, Upland Road, Russell Road, Electric Drive, Fordham Parkway, East Oakland Road, Vineland Road and portions of Wolf and Lake roads. Crews will replace about 8,295 feet of steel and cast iron main installed in the 1950s and 1960s with polyethylene pipe, along with 176 customer service lines. Work is expected to begin in January.

“The new plastic has really good benefits for us,” said Ben Cutler, public affairs manager for Columbia Gas of Ohio. “We call it hundred-year pipe. One of the things I like to joke about is when we get done with this project, folks shouldn’t see us again in our lifetime. There is no corrosion. It’s got some weather variability, so it can expand and contract.”

The new main will accommodate medium pressure, increasing capacity to meet rising demand for natural-gas-fueled electric generators, Cutler said. Service interruptions for residents will be scheduled in advance and last two to four hours per household.

A second project on the west end of Bay Village and the eastern edge of Avon Lake will install about 9,128 feet of 2-inch and 4-inch polyethylene main and replace 244 service lines.

About 85 percent of that work falls in Avon Lake. Bay Village streets affected include Huntington Woods Parkway, Anna Lane, Eagle Cliff Drive and nearby sections of Lake Road. Construction is expected to start in March or April.

“Our goal will be to directional bore as much as we can,” Cutler said, noting the method reduces digging in streets, sidewalks and yards. He plans to return to City Council in March with a construction update.