A Columbus developer has asked Mansfield’s Planning Commission to hit pause on a $130 million mixed-use project, buying two more months to answer neighbors who packed an October hearing to oppose it.
Gary Smith, owner of G2 Planning & Design LLC, filed the delay request on behalf of Highland Real Estate Group ahead of a Tuesday afternoon commission meeting at City Council chambers. In a letter to Mayor Jodie Perry, Smith wrote that questions about infrastructure and utilities raised during the October 27 public hearing require additional testing by both the city engineer and the applicant before the community can get answers.
The request is procedural but essential: under city guidelines, the commission must act on an application within 60 days of opening a public hearing unless the applicant specifically asks for more time. Smith asked that the matter be tabled until the commission’s scheduled meeting on January 26, 2027.
Highland Real Estate Group wants to rezone roughly 64.66 acres of the former Raemelton Farm property along West Cook Road — listed at 1030 Marion Ave. with the Richland County Auditor — to a residential and professional Planned Unit Development.
Under the “Raemelton” master plan, the developer envisions 504 total residential units across four subareas: a mix of apartments and townhomes, 84 attached townhomes specifically, commercial outlots, and a skilled-nursing care facility.
The October 27 hearing drew standing-room-only crowds. Eleven residents spoke against the plan, citing traffic impacts on South Trimble and West Cook roads, the intrusion of commercial lots into a residential area, and potential hits to surrounding property values.
Opposition has since formalized. A “Woodland Cares” group on Facebook is focused on preserving the neighborhood’s residential character and keeping residents informed on land-use decisions. Organizers handed out yard signs, informational materials, and petition sheets opposing the development, along with trash bags for volunteers cleaning up litter along the route.
Perry, a Woodland resident herself, acknowledged the developer’s delay request during an interview on the News Man Weekly podcast published Tuesday. She noted the land is currently zoned R-2, which allows duplexes, multi-family, and townhouse dwellings capped at two stories and a maximum height of 25 feet.
Perry said she wasn’t shocked by the volume of feedback but called the packed chambers “something to see.” She emphasized the process will remain public. “I’m not trying to sneak things through there. It’s a public process for a reason,” she said.
Mansfield, the Richland County seat founded in 1808 and named for U.S. Surveyor General Jared Mansfield, grew into a manufacturing hub after four railroads converged there. By 1888, its largest employer was a cigar factory with 285 workers, and the city later earned the nickname “Carousel Capital of Ohio.” The population stood at 47,534 in the 2020 census.
Regardless of the Planning Commission’s eventual recommendation, Mansfield City Council holds final authority on the rezoning request. The commission meets Tuesday at 3:30 p.m. to consider the delay. If granted, the next substantive discussion is slated for January 26, 2027.