Construction Begins On $309.65M Red Hill Water Treatment Plant in Honolulu

Construction began November 12 on a $309.65 million water treatment plant at Joint Base Pearl Harbor-Hickam, marking the start of field work on a project the Navy says will restore and protect the Honolulu water supply and the aquifer beneath it.

Naval Facilities Engineering Systems Command Hawaii and its project partners held a traditional Hawaiian site blessing to recognize the start of construction for Project P-716, Infraday reported. Hensel Phelps Construction Co. holds the firm-fixed-price contract awarded August 11, according to the SAM.gov award notice (N62478-26-C-0001). The Navy expects construction to finish in August 2029.

The plant is designed to treat up to 10 million gallons a day. That figure describes planned capacity; the volume actually treated will depend on how the water system operates once the project is complete, Infraday reported.

The contract also covers improvements to the Red Hill Pump Station, modifications to the water shaft, transmission piping, electrical distribution, fencing and fire-protection systems — infrastructure that connects the new treatment capacity to the customers it is intended to serve.

“With 30 years wearing this uniform, I’ve stood at many groundbreakings. But today is different,” said Capt. Weurielus “Trey” Johnson, commanding officer for NAVFAC Hawaii, at the blessing ceremony. “Today is not about putting another building on a map or checking off a milestone on a master plan. Today is about delivering on a sacred promise.”

Kahu Kordell Kekoa, a Hawaiian religious leader, performed the blessing, a tradition that recognizes the land, honors those who came before, and asks for guidance and a safe journey for everyone involved in the work, according to DVIDS.

“In Hawaii, anytime you build you must first listen to the land,” Johnson said. “We are grateful for the spiritual stewardship today as we begin this critical work.”

“In Hawaiian culture, there is a profound, sacred relationship between the aina [land], the wai [fresh water] and the people,” Johnson said.

“Water is not just a utility resource, wai is life.” He added: “Our kuleana — our deep, non-negotiable responsibility — is to protect that water and the aquifer that lies beneath our feet. We are here to restore trust, and we are doing it with concrete, steel and unyielding commitment.”

Joint Base Pearl Harbor-Hickam hosts the Red Hill Bulk Fuel Storage Facility, where the November 20, 2021 fuel release contaminated the Red Hill Shaft — one of three wells supplying the base drinking water system — and the groundwater aquifer located 100 feet below the facility.

The August 2029 target applies to construction completion. The Navy’s start-of-work announcement gave no separate date for the first delivery of treated water from the facility.