A social housing scheme of 13 homes in Dublin 18 was due by February 2022; the first contractor was fired and the site sat exposed for months, The Journal reported.
Dún Laoghaire–Rathdown County Council paid the original developer €984,341 before terminating the contract in August 2022. The council had warned the contractor in March 2022 about slow progress, citing the developer’s own explanation of a sick foreman and “difficulty in sourcing labour to manage and carry out the works” and problems getting “solid commitments from sub-contractors,” according to correspondence released under FOI.
After termination, the partially built development lay vacant for more than eight months. Consultant engineers found timber frames and insulation in one block had to be removed after being “exposed to the elements over the past few months,” while drainage pipes on the other block also had to be removed following exposure to sunlight. An emergency contractor was hired in October 2022 for an initial €142,988 to address health and safety risks including “unsuitable material,” exposed trenches and waste.
That bill rose to €195,652 in March 2023 and to €229,702 by July 2023, pushing spending on the unfinished project above €1.2 million.
In March 2024 the council sought a revised budget of over €6.3 million from the Department of Housing — €486,143 per unit. The department “considered high” but did not deem the costs “unreasonable” given the emergency works and the need to finish the homes.
The second contractor completed the project and handed it over in September 2024.
“All payments were made in accordance with the contract,” a council spokesperson told The Journal. The final total cost remains unknown as the council awaits “feedback from the contractor” that finished the build.
The records came to light after a local resident, identified only as Liam, filed a freedom of information request when work appeared to stall.
The department accepted the justification based on the emergency works required and the need to complete the 13 homes.
The approval allowed the council to proceed with the second contractor.
The statement was provided in response to the findings released under the FOI request.
The project was handed over in September 2024.