“Working with GFL has been good. They are responsive to EGLE,” said Scott Miller, a district coordinator for the Michigan Department of Environment, Great Lakes and Energy, at a Nov. 18 meeting of the Washtenaw County Materials Management Planning Committee.
“Since GFL’s taken over ownership the facility’s overall compliance with air quality has been good. They’ve had some violations issued in the last five years or so, but we consider those relatively minor violations,” Miller said. GFL, which operates Arbor Hills Landfill, is seeking a 91-acre expansion on land it owns north of Six Mile Road in Salem Township as the current site nears capacity in about four years.
The county committee is expected to discuss the proposal for several more months before recommending a waste management plan to the county board. EGLE representatives said the landfill has been responsive to recommended changes, though compliance issues remain. “To say they are in compliance, you can say it with a caveat,” said Gary Schwerin, a district supervisor in EGLE’s Materials Management Division. The landfill remains out of compliance for methane migration under Napier Road and is working through the state’s process to address it, Schwerin said. Elevated arsenic levels also persist, with the state allowing GFL time to find a solution.
Since taking ownership from Advanced Disposal several years ago, GFL has invested more than $150 million in site infrastructure since 2022, said Tony Pelletier, GFL’s vice president of post collections support. “Since we took over, our compliance record has improved greatly,” he said.
Pelletier said a “ramp up” of violations for air quality issues occurred in the late 2010s, when Advanced Disposal operated the site. “We’ve made a significant investment in this asset to do the right thing and get it into compliance, where it needs to be today,” he said. GFL replaced gas wells, upgraded gas collection, relocated a million cubic yards of waste to lined areas and installed perimeter air emission monitors. A 2022 settlement with the state over a 2020 lawsuit brought by Attorney General Dana Nessel’s office required $2.3 million in fines and environmental projects.
Northville Township Supervisor Mark Abbo called the meeting “a lot of sugar-coating of the issue,” citing a documented history of environmental non-compliance and repeated enforcement actions by EGLE and the Ypsilanti Community Utilities Authority. He pointed to an April incident when Arbor Hills bypassed its wastewater treatment system, discharging PFAS and other chemicals into YCUA’s system.
Pelletier said a former employee bypassed filtration without notifying YCUA, was let go and replaced, and GFL rewrote its policy in response.
Brian Turnbull also opposed the expansion, citing concerns for Johnson Creek. “The creek is the holy waters for all of southeastern Michigan” for brown trout, Turnbull said. The committee will continue its review in the coming months.