Fargo-Moorhead Diversion Nearly Complete, But Flood Insurance Relief May Wait Until 2030

The Fargo-Moorhead Diversion is nearly finished, but flood-insurance requirements could stay in place until 2030, officials said Friday.

The project is expected to be substantially complete this fall and ready to protect the metro area next spring, InForum reported. Yet the Federal Emergency Management Agency must still certify the system and revise flood maps before roughly 12,000 homes can be removed from the 100-year floodplain — a process that could take until 2030.

Metro Flood Diversion Authority Director of Engineering Kris Bakkegard said the authority has been submitting data to FEMA for years rather than waiting for final construction. “They’ve agreed to look at things in an almost complete state, and then they’ll do a more final review once we get everything in, once construction is totally completed, just to verify that there weren’t any significant changes,” Bakkegard told InForum.

FEMA Region 8 staff are currently reviewing Flood Insurance Rate Map revisions for North Dakota, the agency said in a statement. “Given the scale and complexity of the project, both the construction and mapping components require coordination and collaboration across all stakeholders to streamline the mapping component,” the statement said. “FEMA is reviewing modeling and levees as they are being done instead of waiting to start reviews once the project is complete.”

Since the record-setting flood in 2009, Fargo has built 28 miles of levees and floodwalls, Assistant City Engineer Nathan Boerboom said. He hopes FEMA will approve those levees by the end of winter or early spring.

“FEMA has fully acknowledged that they have to approach this remapping project differently than how they do elsewhere in the country, just due to the sheer size of it and the importance of remapping the floodplain for a community,” Boerboom told InForum.

The Metro Flood Diversion Authority (MFDA) operates as a joint powers authority established to govern the $3.2 billion Fargo‑Moorhead Area Diversion, with Jacobs serving as program manager and P3 advisor since 2011.

MFDA Executive Director Joel Paulsen noted in 2022 that the Authority’s innovative public‑private partnership — the first flood‑protection P3 in the U.S. — combined local sales‑tax revenue, state funds, $500 million in federal appropriations, private‑activity bonds and an EPA WIFIA loan to keep construction on track for a 2027 completion date.

Once maps are updated, the Diversion Authority estimates annual flood-insurance savings of $30 million to $50 million for area homeowners. The system will hold Red River floodwater behind a 22-mile earthen dam south of Fargo and divert it through a 30-mile channel, with levees and lift stations protecting the cities from elevated river levels.

Crews are now finishing seeding, cleanup and final inspections. “Generally speaking, we have all the major components of the project constructed and ready to fight a flood,” Bakkegard said.