The Fargo-Moorhead Area Diversion project is on track for substantial completion this fall, positioning the $3.2 billion system to shield the metropolitan area from Red River flooding next spring.
The project spans a 22-mile earthen dam south of Fargo and a 30-mile diversion channel designed to route floodwaters around the metro. Since the record 2009 flood, Fargo has built 28 miles of levees and floodwalls as a complementary defense.
Federal Emergency Management Agency certification and revised Flood Insurance Rate Maps are required before roughly 12,000 homes can exit the 100-year floodplain, lifting mandatory flood-insurance requirements for properties with government-backed mortgages. The Diversion Authority estimates annual premium savings of $30 million to $50 million once maps are updated, according to northdakota-express.com.
Metro Flood Diversion Authority Director of Engineering Kris Bakkegard said the authority hopes to finish FEMA certification in about three years, faster than the typical five-year timeline.

“We’re trying to condense that as much as we possibly can, and we’ve been working hard, collaborating with FEMA and all our other agency partners to advance as much as possible of those reviews,” Bakkegard told northdakota-express.com.
FEMA Region 8 staff are currently reviewing Flood Insurance Rate Map revisions for North Dakota. The agency said in a statement that both construction and mapping components require coordination across stakeholders to streamline the mapping component, and that FEMA is reviewing modeling and levees as they are being done instead of waiting until the project is complete.
City of Fargo Assistant City Engineer Nathan Boerboom said FEMA has fully acknowledged it must approach this remapping project differently than elsewhere in the country due to the sheer size and the importance of remapping the floodplain for the community. He hopes FEMA will approve the city’s levee review by the end of winter or early spring 2027.
Wisevoter reported the city hopes for a levee review decision by early spring 2027, with the project expected to be ready to protect the metro next spring, while certification could take until 2030.
Crews are completing seeding, cleanup, and final inspections of project components. The Diversion Authority and its partners have been submitting information to FEMA for review over the past couple of years.
“Generally speaking, we have all the major components of the project constructed and ready to fight a flood,” Bakkegard said.