Feds Back $4B Wyoming Intertie That Would Double Grid Transfer Capacity

The U.S. Department of Energy announced Nov. 17 a conditional $2.8 billion loan guarantee for a $4 billion transmission line that would double electricity transfer capacity between the eastern and western grids, with construction targeted to begin in 2030.

  • 106‑mile Wyoming Intertie adds 1,800 MW of bidirectional HVDC capacity between the Southwest Power Pool and the Western Interconnection.
  • DOE estimates $39 billion in avoided costs for ratepayers across 17 states over 30 years.
  • Route runs from Laramie River Station near Wheatland to PacifiCorp’s Aeolus substation near Medicine Bow.
  • Financing remains conditional on technical, legal, environmental and financial milestones.

Federal backing announced

The Energy Department’s Office of Energy Dominance Financing disclosed the commitment Nov. 17, describing the Wyoming Intertie as an interregional project whose “impact and benefits are far beyond local Wyoming counties,” Director Gregory Beard said in a Tuesday press conference. Houston‑based developer Grid United would string high‑voltage direct‑current lines across roughly 90 percent state and federally owned land in Platte, Albany and Carbon counties, AP reported.

Technology and capacity

Because the eastern and western grids operate asynchronously, the intertie requires voltage‑source converter stations that account for more than half the project’s nearly $4 billion cost, Beard told Engineering News‑Record. The 1,800 MW link would more than double existing transfer capability, allowing operators to move power during congestion, generation outages or extreme weather without requiring the two systems to operate in phase.

Photo: enr.com

Savings claims and caveats

DOE modeling projects $39 billion in avoided costs over 30 years for consumers in Wyoming and 17 other states. “The bridging of these neighboring systems with a transmission line provides more reliable energy flows, lowers ratepayer electricity bills and stabilizes the grid, especially during extreme weather conditions,” Beard said.

Wyoming Energy Authority Director of Energy Market Development John Jenks told WyoFile the line “adds flexibility to energy being dispatched onto the grid,” but cautioned: “It might be a stretch to say it will (lower monthly bills), but that’s the theory behind it.”

Project origins and grid function

First conceived in 2022 and refined through several iterations, the Wyoming Intertie would employ high‑voltage direct‑current converter facilities to link the Southwest Power Pool and the Western Interconnection, which operate asynchronously, Gregory Beard told Engineering News‑Record. The converter stations allow operators to move electricity between the two grids during periods of high demand, generation outages and extreme weather without requiring the systems to run in phase.

Beard described the project as an interregional asset rather than an interstate or local transmission line, saying its “impact and benefits are far beyond local Wyoming counties.” He credited President Donald Trump’s “energy dominance” initiatives, including the Strengthening the Reliability and Security of the U.S. Electric Grid executive order, for advancing the effort.

Permitting and timeline

Beard said the predominantly public‑land route avoids condemnation battles: “There will not be protests in the street over condemning land to get this line up.”

Grid United says on its project website that the route remains proposed until county, state and federal regulators approve it, and that construction will commence only after land rights and approvals are secured. The three‑year build is expected to start around 2030, targeting completion near 2033.

The financing commitment remains conditional on Grid United satisfying all technical, legal, environmental and financial requirements before definitive agreements are executed and funds disbursed.