Final Girders Placed on Kingman Flyover, $106M I-40/US 93 Interchange 85% Complete

Crews hoisted the final girders into place on a Kingman flyover bridge this week, pushing the $106 million Interstate 40 and US 93 interchange project to 85 percent completion, KTAR News reported.

The 1,100-foot structure will carry southbound US 93 traffic onto eastbound I-40, removing the traffic signal at Beale Street that has long backed up the Phoenix-to-Las Vegas corridor. ADOT said the bridge sweeps over westbound I-40 at Clack Canyon and is the project’s most visible element.

Final deck pour set for December

The 10 girders installed this week form two of the bridge’s seven spans, each roughly 160 feet long on a 43-foot-wide deck. Crews will pour the concrete deck in December, according to ADOT.

Work continues on the mile-long ramps that will allow nonstop flow between the highways, and on widening the eastbound and westbound White Cliffs bridges — also 85 percent finished. Daytime and overnight lane restrictions remain in effect, though Beale Street exits stay open for local businesses, Route 66 access and downtown Kingman.

ADOT advances Kingman interchange toward 2027 opening

ADOT said the interchange will eliminate the traffic signal at Beale Street that has long backed up the main route between Phoenix and Las Vegas.

Next construction phases target deck pour and ramp paving

With the 10 final girders in place forming two of the bridge’s seven spans, crews will pour the concrete deck in December.

ADOT said widening of the eastbound and westbound White Cliffs bridges is also 85 percent finished, while daytime and overnight lane restrictions remain in effect.

The completed interchange will encompass six miles of new or widened pavement, including a mile of new highway northwest of the existing Beale Street connection. Plans also call for widening more than a mile of I-40 in both directions to Stockton Hill Road, adding a northbound US 93 merge lane, rehabilitating four I-40 bridges and building two miles of sound walls west of Stockton Hill Road.

ADOT began construction in July 2024. The agency targets a full opening in spring 2027. A September milestone opened a 239-foot tunnel — the project’s second — which ADOT expects to handle more traffic than the first.