The Federal Railroad Administration is withdrawing $659 million in grants awarded on Aug. 14 for Amtrak’s Chicago maintenance relocation, killing a land deal that underpinned a proposed White Sox stadium.
- FRA pulls $572 million for a new Midwest Maintenance Facility and $87 million for bridge work at Canal Street Yard.
- Agency bars Amtrak from buying Canal Street Yard and from selling its 14th Street Yard.
- Amtrak must submit a modernization plan for 14th Street Yard or risk losing the remaining grant money.
- Justin Ishbia, who holds an option to buy the White Sox after 2034, had committed over $125 million to the project.
Cost overruns drive federal reversal
FRA Administrator David Fink told interim Amtrak President Byl Herrmann in a letter obtained by Trains.com that due diligence exposed “major, previously unquantified infrastructure costs that render the Canal Street relocation fiscally untenable.” An independent analysis identified approximately $400 million in additional costs over 50 years to stabilize 17 bridges and viaducts at the proposed Bridgeport site, Trains.com reported.
Further operational assessments revealed Amtrak would need to retain rail infrastructure it had planned to sell, creating a shortfall in its required non-federal match. The additional work would require another $700 million or more in capital investment, according to Fink’s letter.
Stadium plan loses its land
The decision blocks the public-private partnership between Amtrak and Canal Edge LLC, the firm led by White Sox minority owner Justin Ishbia. Ishbia had committed more than $125 million to build the new maintenance facility and spearhead redevelopment of the 14th Street property into a mixed-use project known as The Railyards, which included a potential ballpark, Trains.com reported.
The FRA’s prohibition on selling the 14th Street Yard removes the land from Ishbia’s control. “The federal government is now directing the railroad to remain on the very property he had intended to redevelop,” Trains.com noted.

Amtrak pivots to existing yard
Amtrak said it will focus on redeveloping its current 14th Street Yard. “Amtrak, in consultation with USDOT, is shifting its focus to redevelopment of our existing 14th Street Yard as a better long-term approach to modernizing our Chicago maintenance facilities,” the railroad said in a statement to Fox Chicago.
“FRA has agreed to rescope the grant to reflect the new direction of the project.” The FRA will consider allowing the $572 million grant to fund limited modernization at the current site, which Amtrak said offers better operational access to Chicago Union Station.
Opposition mounts before federal reversal
Construction had been expected to start this fall before the FRA intervened.

Earlier in 2024, the White Sox and developer Related Midwest had unveiled renderings for a ballpark at The 78, a 62-acre South Loop site along the Chicago River, but public financing for that plan stalled in Springfield, according to SoxOn35th.
Ishbia’s option and the lease timeline
White Sox minority owner Justin Ishbia holds an option to purchase the team after the 2034 season, while the club’s lease at Rate Field runs through 2029, Chicago Urban Daily News reported. The South Loop stadium site that had been taking shape is now off the table for the foreseeable future.
Canal Street plan faces resident opposition
The Canal Street plan faced strong resistance from Bridgeport residents over noise and environmental concerns. A Chicago City Council committee, Cook County officials, and the Rail Passengers Association had urged a full environmental review before proceeding, Chicago Urban Daily News reported. Construction had been expected to begin this fall.
Amtrak must now submit “a reasonable, well-justified scope of work to modernize the 14th Street Yard” to keep its federal dollars, Fink wrote. Failure to do so may result in withdrawal of all grant funding tied to the Midwest Heavy Maintenance Facility project.