A Navy women’s health clinic will reclaim examination space lost to administrative sprawl through a phased renovation that keeps patients in care throughout construction, the U.S. Army Engineering and Support Center, Huntsville announced Monday.
- 24,000 square feet on the fourth floor of Building 2 at Naval Medical Center Portsmouth will be modernized over approximately two years.
- A seven-phase plan limits active construction to no more than 10 exam rooms at a time so gynecologic, fertility and oncology services continue uninterrupted.
- The project converts offices back to exam rooms, adds medical headwalls, LED lighting and accessibility-compliant restrooms, and groups care teams together for a more logical patient flow.
- No structural expansion is planned; the work is an interior modernization of a 50-year-old facility.
The Women’s Health Department occupies space in a medical facility dating back 50 years. Over decades, rising staffing needs turned rooms originally designed for patient examinations into administrative offices. “Areas that were obviously exam rooms became offices,” said Ronald Johnson, the Huntsville Center project manager attached to the renovation. The redesign reverses that trend, reducing the administrative footprint and increasing the exam and procedure footprint, Johnson told Army.mil.
Currently, medical teams operate in areas not arranged around how they work together. The new layout groups team members so patients check in and proceed directly to the area assigned to their care team. The change aims to benefit both patients moving through the clinic and the professionals providing care, the Army.mil report states.
Building improvements involve swapping out worn flooring, ceilings, doors and other interior finishes; adding energy-efficient LED lighting; refreshing medical equipment connections; and updating reception areas with new desks, counters and security features.
Public restrooms in the main waiting area will be reconstructed to meet federal accessibility requirements. Some examination and procedure rooms will receive new medical headwalls — built-in wall units that provide access to medical gases and vacuum systems used during patient care.
Ronald Johnson, the Huntsville Center project manager attached to the renovation, said the redesign reverses decades of incremental conversion that turned examination rooms into administrative offices as staffing grew.
The new layout groups care teams together so patients check in and proceed directly to the area assigned to their team, a change intended to benefit both patients moving through the clinic and the professionals providing care, Army.mil reported.
Closing the department was never a practical option because it provides gynecologic care, fertility treatment and gynecologic oncology, Army.mil reported. Instead, a seven-phase approach limits active construction to no more than 10 examination rooms at a time over approximately two years.
The clinic provides gynecologic care, fertility treatment and gynecologic oncology. Closing the entire department was never a practical option. Instead, Huntsville Center devised a carefully coordinated, seven-phase construction approach designed to keep the clinic operational throughout the renovation, Army.mil reported.
The schedule covers roughly two years, with the contractor restricted to working on no more than 10 examination rooms during any single phase, allowing medical personnel to continue caring for patients while construction advances in manageable sections. The project demonstrates how thoughtful design, careful construction planning and close coordination with the customer can extend the usefulness of existing federal facilities, the Center said.