I-80 Gold Corp. began production mining at its Archimedes underground deposit on Monday, shifting to a lower-cost oxide heap-leach route that targets first gold recovery in the first quarter of 2027, The Northern Miner reported.
The Nevada miner originally planned to process mostly sulphide ore through a third-party mill, recovering 58% of contained gold.
It now intends to stockpile refractory sulphide material for its own Lone Tree plant, slated for commissioning in the fourth quarter of 2027. “A lower-cost oxide route supports near-term cash flow ahead of Lone Tree, though the contribution remains subject to quantification with 2027 guidance,” National Bank Financial mining analyst Don DeMarco wrote in a note Tuesday.
Construction started in September 2025 and has progressed largely in line with the March 2025 preliminary economic assessment, with lateral development reaching approximately 3,600 metres, according to TipRanks, which cited the company’s filing. Metallurgical testing confirmed oxide material from the upper 426 Zone is amenable to heap leaching at lower overall processing costs than the Lone Tree oxide mill circuit. The contractor is exceeding planned productivity in that zone, TipRanks reported.
Total project capital is now projected at roughly $57.3 million (C$82 million) due to expanded surface infrastructure, roughly 21% above the $47.3-million figure in the March 2025 assessment. Some of the oxide lies outside the mineral resource estimate supporting that assessment and has not been classified as resources or reserves. I-80 expects to issue production guidance early next year.
Seven underground rigs are drilling the lower 426 and Ruby Deeps zones in a programme of about 55,000 metres across 140 holes, with completion expected in the second quarter of 2027 to support a feasibility study in the second half. On Tuesday morning in Toronto, I-80 shares fell 1.3% to C$1.52, giving the company a market value of about C$1.3 billion ($922 million). The stock has traded between C$1.34 and C$3.04 in the past year.
Resource base updated at year-end 2025
The figures apply to the Archimedes deposit at the Ruby Hill property, which the company acquired in 2021.
The company said that some oxide material lies outside the mineral resource estimate supporting the March 2025 preliminary economic assessment and has not been classified as resources or reserves. I-80 expects to issue production guidance early next year to quantify the oxide contribution further.