Idaho Supreme Court Voids Presale Condo Contracts Over Missing Plans and Specifications

The Idaho Supreme Court ruled on September 24 that two presale contracts for condominium units in Bonner County are invalid and unenforceable because they lacked attached plans and specifications, leaving the scope of work and finish materials undefined.

The court affirmed a district court judgment that denied buyers’ request for specific performance and awarded the developer attorney fees as the prevailing party.

The decision, Schuster v. Milbrath, 597 P.3d 541 (Idaho 2026), centers on purchase and sale agreements (PSAs) for two units in the Harrison Heights subdivision at Schweitzer Village. Developer Benjamin Milbrath used the Idaho Association of Realtors’ 2019 Form RE-22, “Pre-Sold New Construction,” for agreements with Ryan and Aaryn Schuster and other buyers in 2020 and 2021, according to the Supreme Court opinion filed in the June 2026 term.

Each PSA stated the buyer was “purchasing a custom built residence not based on a model, but on detailed Plans and Specifications,” which were “attached and incorporated herein by reference,” and that those documents would contain the “grade and type of materials used in finishing the residence or a dollar allowance for such items.”

None of the PSAs attached any plans or specifications. After COVID-19 supply-chain disruptions increased construction costs, the parties disputed whether the contract price covered basic or upgraded finishes and whether Milbrath had demanded a price increase. The Schusters sued for breach of contract and sought specific performance to compel construction at the original prices.

The Bonner County district court, Judge Susie Jensen presiding, held a bench trial and found the PSAs missing essential material terms — specifically the absent plans and specifications — which left the scope of work, finishes and price adjustments undefined.

The court concluded no enforceable contract was formed, denied specific performance, ordered Milbrath to return deposits, and deemed him the prevailing party entitled to attorney fees and costs. It also conditioned a stay of judgment pending appeal on the posting of an additional $195,000 bond.

The Supreme Court affirmed. Justice Roger Meyer wrote that the scope of work is a material term in a construction contract and that the PSAs’ conflicting references to a base “Model 185-D design” and to custom plans and specifications — which would have allowed modifications through a change-order process — failed to establish what portion of the purchase price covered builder-grade versus high-end finishes.

The court further held that the contract’s selection clause, which asked buyers to choose colors and materials at the seller’s request, could not fill the gap because it depended entirely on the missing baseline documents. Without those plans, the clause failed to identify which finishing materials the purchase price included, which cost extra, whether an allowance applied, or what standard governed the buyer’s selections.

The buyers’ challenge to the additional bond was deemed moot given the disposition of the contract claims. The Supreme Court upheld the district court’s award of attorney fees to Milbrath and granted him attorney fees and costs for the appeal as the prevailing party. Stoel Rives LLP and Hawley Troxell Ennis & Hawley LLP represented the Schusters; Siddoway Law Firm PLLC represented Milbrath.