INL Receives TRIGA Fuel for MARVEL; December Criticality Target in View

  • Fuel fabricated at Framatome’s CERCA plant in Romans, France, under an $8.4 million DOE contract awarded in November 2023.
  • Final element completed Oct. 30; INL team inspected and signed End of Manufacturing Report Nov. 6.
  • Fuel shipped Nov. 13, arrived at Transient Reactor Test Facility Nov. 19.
  • INL still aims for a dry criticality in December, though the project’s page lists 2027.

Abdalla Abou-Jaoude, who leads MARVEL at INL, said the Nov. 19 shipment keeps the reactor on schedule to go critical, dry, by year end.

“The fuel left the plant on November 13, and by November 19 it was in Idaho,” he wrote in a Nov. 13 LinkedIn post. Ralf Gathmann of Framatome’s CERCA business confirmed INL accepted all 37 elements during the inspection visit in France.

The fuel is uranium-zirconium hydride clad in stainless steel, classified as high-assay low-enriched uranium (HALEU).

TRIGA International — a Framatome and General Atomics joint venture the DOE calls the world’s only TRIGA fuel supplier — manufactured the elements at its Romans facility. The hydrogen in the zirconium hydride provides a prompt negative temperature coefficient: as fuel heats, it slows neutrons less effectively and the reaction backs off automatically. General Atomics says its prototype was pulsed past 1,000 megawatts and settled within milliseconds.

When fabrication began in early 2024, DOE expected first fuel in spring 2025. Nuclear Engineering International reported a July or August 2026 delivery in March. The MARVEL team told the ANS conference in June it expected fuel in October and planned two months of readiness work before a December criticality.

The Nov. 19 arrival compresses that window to roughly six weeks.

INL’s project page still lists dry criticality in 2027, but the lab’s October release and Abou-Jaoude’s post both point to December. Full-power operation with sodium-potassium coolant routed to Stirling engines and an industrial-heat loop is slated for 2028.

INL selected five initial user teams in December 2025: Amazon Web Services for modular data-center pairing, GE Vernova for remote and autonomous operation testing, Radiation Detection Technologies for sensor trials, DCX USA and Arizona State University for AI data-center load studies, and a Shepherd Power, NOV and ConocoPhillips group for a small desalination pilot.

INL said final agreements were expected to be announced in 2026; no signings have been publicly announced.

The next milestone is fuel loading into the 15-foot, 85-kilowatt-thermal reactor at TREAT. As of the lab’s Nov. 19 post, the fuel is on site and the December dry-criticality target stands.

Idaho National Laboratory (INL) serves as a cornerstone of U.S. national research, particularly in nuclear science, with a scope that encompasses developing advanced reactors and testing nuclear technologies. Additionally, INL selected initial user teams in December 2025 to test modular data-center pairing and remote operation capabilities, demonstrating its role in bridging nuclear innovation with industrial applications.