Madison will ban hyperscale data centers outright and cap every new facility at 75,000 square feet under an ordinance introduced Friday, City of Madison, WI reported.
The move replaces a one‑year moratorium that expires January 24, 2027, and would mark the first time a Wisconsin municipality has used zoning authority to permanently block the massive server farms that have strained power grids and water supplies in Virginia, Texas and Arizona.
Mayor Satya Rhodes‑Conway framed the proposal as a shield against an industry that “will foist a data center on our community without accountability or regard for the potential negative impacts,” while still permitting the smaller computing facilities that have operated locally for years without complaint.
“Madison residents are rightly concerned that a powerful industry will foist a data center on our community without accountability or regard for the potential negative impacts. This strong proposal will prevent that from happening.”
Mayor Satya Rhodes‑Conway
No applications for new data centers are pending, city staff confirmed. The ordinance creates three tiers: facilities up to 10,000 square feet restricted to certain business and commercial zones; 10,000‑to‑50,000‑square‑foot centers limited to employment and campus‑institutional districts; and 50,000‑to‑75,000‑square‑foot centers allowed only in heavy‑industrial areas at least 500 feet from residential, mixed‑use or commercial zoning and 300 feet from other non‑industrial districts.
Any center larger than 10,000 square feet must submit a noise‑mitigation plan before construction and enclose all external mechanical equipment and backup generators behind solid walls. A 1,000‑foot separation requirement between lots hosting centers over 10,000 square feet effectively bans multi‑building campuses.

WTMJ noted the moratorium, approved in 2025 as a first‑of‑its‑kind move in Wisconsin, cannot be extended indefinitely under state law, forcing the city to codify permanent rules.
WKOW added that the Common Council will introduce the measure at its November 24 meeting, after which it moves to the Plan Commission for a first review on November 30, 2026, the Business and Economic Resources Committee on December 16, 2026, the Sustainable Madison Committee on December 21, 2026, a second Plan Commission hearing on January 11, 2027, and a final council vote on January 12, 2027. Each committee will accept written public comment.
IBMadison reported that an earlier draft defined “hyperscale” as anything above 100,000 square feet and was previewed at a virtual public meeting on October 27. The introduced ordinance tightens that threshold to a 75,000‑square‑foot hard cap, a change city planners said reflects feedback gathered during the moratorium period.

Madison officials acknowledge the limits of local authority — state law restricts direct regulation of energy and water use — but say land‑use powers give them a legal foothold to shape the physical footprint of any future project.
The Plan Commission takes first testimony on November 30.