Omaha City Council will vote Dec. 8 on a $12.4 million land purchase that clears the way for a $181 million joint police and fire headquarters at the Crossroads redevelopment site, Nebraska Public Media reported.
Voters approved a $155 million public facilities bond in early November with roughly 69% support, Douglas County Election Commission unofficial results show. The bond authorizes general obligation bonds through Dec. 31, 2034, for a list of city facilities beyond the headquarters, Oversight Justice reported. The ballot question listed police buildings, fire stations, branch libraries, park maintenance facilities, auditorium support facilities, arena and convention center facilities, public works storage facilities and citywide building renovations. The ballot put the approximate cost to taxpayers at $155 million “plus interest.”
It also said approval “will not incur any increases in the debt services tax levy rate of the City of Omaha over the levy increase approved in 2020.” Ordinance 44779 lets the council issue the bonds “from time to time, but no later than December 31, 2034 without further vote of the electorate.”
It allows the money to cover “necessary plans and specifications” and “acquiring such land and easements as may be required.” It excludes “the cost of City construction equipment and payment of salaries to City employees.”
The 3.2-acre parcel at 75th and Cass streets would be bought from Crossroads Block A, LLC for $12,428,532 based on fair market value, said Jennifer Taylor with the city law department. Ordinance 44886 authorizes the purchase and sale agreement.

Locating the headquarters outside downtown is unusual for Omaha, but Mayor John W. Ewing Jr.’s chief of staff Tom Warren said building new at Crossroads avoids an estimated $45 million in extra costs compared with renovating the current downtown building or constructing a high rise.
“We’d be looking at potentially $45 million in savings, and so the Crossroads site offers a lot of advantages,” Warren said.

The four-story, 275,000-square-foot facility is planned between Cass and Chicago streets near 74th Avenue. It would house more than 300 administrative personnel from the Omaha Police Department and Omaha Fire Department, the mayor’s office said in a Nov. 4 release.
Omaha’s existing downtown police headquarters was built in 1970 and spans 112,000 square feet. Police Chief Todd Schmaderer has said the space lacks proper ventilation and is regularly tested for asbestos.
Design work continues into late 2027. Construction is scheduled to begin January 2028 with completion targeted for spring 2030.