Pennsylvania American Water Nears $143M Plant to Replace 1918 Facility

Pennsylvania American Water is nearing completion on a $143 million treatment plant to replace a facility built in 1918, WHYY reported.

The new Lock 57 facility in East Vincent Township will produce up to 11 million gallons a day, more than triple the Shady Lane plant’s 3 million-gallon capacity. Demand in the Royersford area has already reached 4.5 million gallons daily, forcing the utility to lean on neighboring systems, according to company figures cited by WHYY and ctenews.com.

“This area has just grown by leaps and bounds in the last generation, and the infrastructure here has reached the end of its lifespan and doesn’t meet the demand that the region has,” said John Keleman, the company’s manager of external affairs, to WHYY. The 10-year project will serve about 50,000 residents across northern Chester County and western Montgomery County.

Lock 57 is expected to enter service by mid-2027, WHYY and ctenews.com reported. Lock 57 will use ultraviolet disinfection and replace chlorine gas with sodium hypochlorite, ctenews.com reported. The plant will also include a system to treat PFAS, often called “forever chemicals,” intended to help the utility meet federal regulations aimed at reducing the chemicals to almost zero by 2031.

Separate chemical rooms with dedicated feed systems and piping are designed to reduce risks tied to storing pressurized chlorine gas, Justin Brame, a senior operations manager for Southeastern Pennsylvania, said. Shady Lane will remain online until Lock 57 is ready to produce water. The company plans to demolish the old plant eventually but has not announced when that work will happen, ctenews.com reported. The project is funded by ratepayers.

Separate chemical rooms with dedicated feed systems and piping are designed to reduce risks tied to storing pressurized chlorine gas, Justin Brame, a senior operations manager for Southeastern Pennsylvania, told ctenews.com.

The company said some equipment at the century-old plant can no longer be acquired, which contributed to the replacement decision.

Drone shot of an advanced water purification plant surrounded by trees
Photo: ctenews.com

The project is funded by ratepayers, both WHYY and ctenews.com noted.