New Mexico’s largest electric utility filed a proposal Tuesday for a 19% rate increase for most residential customers, citing grid modernization and renewable energy costs.
If approved by the Public Regulation Commission, approximately two-thirds of residential ratepayers would see a roughly $22 increase in monthly electrical bills, according to the filing. The utility’s proposal, estimated at more than 13,000 pages, requests $172.2 million from ratepayers, Source New Mexico reported.
Reasons for the Rate Hike
PNM’s filings state the increase would pay for approximately $87 million to “harden, improve and expand” the electric system, along with $90 million in renewable energy and energy storage costs. The utility also needs $54 million for increased operating and maintenance expenses and other costs “associated with wildfire mitigation, cybersecurity protections and technology advancements.”
Low-Income Customer Protections
While the proposed rate increase would take effect Oct. 1, 2027, PNM is also rolling out a first-ever program to shield some customers. A 2025 state law enabled the utility to create a program for low-income ratepayers.
Customers whose income is 200% or less of the federal poverty limit—about $66,000 for a family of four—would see, on average, only a $1 increase each month, Goodman said. She estimated one-third of New Mexico’s residential ratepayers would qualify.

“We’ve really worked to incorporate that low-income discount to offset any impact to customers from this,” Goodman said. “So it’s negligible to them.”
Rate Increase Details Emerge
The company stated the funds are needed for its clean energy transition, disaster resilience improvements, and cybersecurity protections.
Separately, PNM in 2024 secured PRC approval for a rate hike averaging $11 more per month for most customers, which began appearing on bills in July 2025. The utility also proposed the state’s first data center rate, ensuring those facilities bear their full electricity costs without passing them to ordinary ratepayers.
Utility Defends Request
PNM stressed that the rate increase filing is unrelated to the ongoing case involving its potential sale to Blackstone.
Goodman reiterated that the price hike stems from rising costs and growing demand, noting the utility’s system hit multiple new peaks this summer. She emphasized efforts to minimize impacts, particularly for low-income households qualifying for an 18% discount on bills.

Criticism and Regulatory Process
In a statement Tuesday, she called it “outrageous” that PNM would seek a rate increase while the PRC is considering a potential acquisition by private equity firm Blackstone. “These proceedings cannot be treated as though they have no relationship to one another,” she said.
PNM officials said the rate increase and the potential acquisition are “separate regulatory processes with different purposes” and that its proposed increase reflects “investments needed to serve customers, regardless of the acquisition.”
PNM is an investor-owned utility, as confirmed by its ultimate parent company TXNM Energy, which is publicly traded and pending acquisition by Blackstone Inc. This structure directly influences rate case approvals, as seen in the 2024 rate hike docket 24-00089-UT, where PNM requested a 10.45% return on equity (ROE) and a $174.3M revenue increase, which was later settled with an approved ROE of 9.45% and a $52.5M revenue change.
The utility’s investor-owned status also dictates its rate mechanism, which is traditional and settled, with decisions made by the New Mexico Public Regulation Commission.
The filing initiates a hearing process expected to take between 10 and 13 months. Customers can submit written comments or speak at public meetings, and the PRC will hold a public hearing before making a decision.