Salt River Project Delays Bartlett Dam Expansion to 2045

The Salt River Project has pushed back completion of the Bartlett Dam expansion from 2035 to 2045, a decade-long delay that leaves the Phoenix metropolitan area without a major new water source as Arizona prepares to lose 760,000 acre-feet of Colorado River water annually starting next year.

SRP informed stakeholders of the delay in August, Axios reported. The project, estimated at $4.4 billion, would raise the dam 100 feet to capture Verde River runoff that currently flows downstream. SRP says the expanded reservoir would hold enough additional water to supply one million households for a year, while the Kyl Center for Water Policy at Arizona State University estimates it would yield roughly 90,000 acre-feet annually for up to 23 participating entities.

Phoenix water resources management advisor Max Wilson told Axios the holdup stems from a change in permitting strategy. The original plan called for simultaneous permitting, but the U.S. Bureau of Reclamation now requires the reviews to be done sequentially.

“The federal government has made choices that significantly reduce the availability of Colorado River water,” Wilson said. “The feds should speed up the projects that are necessary for us to be able to live in that world that they’ve created for us.”

Photo: newmediaphoenix.com

Sean Heath, deputy manager of Reclamation’s Phoenix area office, said in a statement to Axios: “Reclamation continues to seek project efficiencies and remains committed to the expedited project development process.” He did not answer a question about the reason for the delay.

Without the expansion, SRP has been forced to release excess water during heavy rains, including roughly 200,000 acre-feet earlier this month. Sarah Porter, director of the Kyl Center, said the delay means a decade more of drawing down groundwater supplies that are not easily renewed.

SRP and Reclamation are working on a draft environmental impact statement that could be ready as soon as December. SRP anticipates submitting a feasibility study to Congress by early 2028, which would then have to allocate funding for the project. The next formal public review meeting is scheduled for early next year, according to New Media Phoenix.

Isometric editorial illustration of a plain concrete dam face holding back a still reservoir
Photo: wisevoter.com

The U.S. Bureau of Reclamation now requires the Bartlett Dam expansion to undergo permitting sequentially rather than simultaneously, according to Phoenix water resources management advisor Max Wilson. Wilson told Axios that this shift from the original parallel approach is the primary reason for the decade-long delay.

Without the project, local water managers emphasize that maximizing storage capacity remains essential for future supply reliability across the region.

The Salt River Valley Water Users’ Association, half of the Salt River Project umbrella, serves as the primary water provider for much of central Arizona and operates six reservoirs along the Salt and Verde rivers, including Bartlett Dam on the Verde River.

This infrastructure captures runoff that SRP says could supply one million households annually, a critical buffer as Arizona prepares to lose 760,000 acre-feet of Colorado River water starting next year.

Because the original dams were among the first five reclamation projects approved under the National Reclamation Act of 1902, the U.S. Bureau of Reclamation retains a central role: it now mandates sequential rather than simultaneous permitting for the $4.4 billion Bartlett Dam expansion, a shift SRP says is the primary reason completion has slipped from 2035 to 2045.

“Allowing hundreds of thousands of acre-feet of water to flow down the Salt River because the folks involved were unable to get the paperwork filled out is not an acceptable answer for any of us,” Wilson said.