Tapani Inc. bid $50.38 million to rebuild Portland International Airport’s north runway, the lowest of four offers opened November 12.
- Tapani Inc. submitted the apparent low bid of $50,380,000 for PDX North Runway Rehabilitation.
- Three other contractors bid between $51.4 million and $60.8 million.
- Port Commission approval is anticipated December 9, with FAA grant funding expected early April 2027.
- Onsite work is scheduled to begin around May 3, 2027, with substantial completion by September 24, 2027.
The Port of Portland opened bids November 12 for Solicitation No. 2026-14659, covering Runway 10L-28R and associated taxiway work. Tapani Inc. came in at $50,380,000. Kerr Contractors bid $51,367,263.60, K & E Excavating, Inc. bid $54,571,236, and Granite Construction bid $60,755,935, according to the Oregon Bid Network.
The project includes mill-and-inlay paving on the north runway and shoulders, reconstruction of the north shoulder and blast pad sealing, and upgrades to Runway 10L navigation aids to Category II/III standards. Taxiways A1, A2, A3, A5, A6, K1, and T will be rehabilitated and widened, while Taxiway A4 will be relocated. The work also covers lighting, signage, electrical vaults, storm drainage, markings, grading, and seeding, GovTribe reported.
The Port Commission is expected to consider award on December 9. Contract award depends on FAA Airport Improvement Program grant receipt, anticipated in early April 2027. Notice to proceed for onsite work is targeted for May 3, 2027. The contractor must substantially complete Work Area 4 within 28 consecutive days of the agreed start date, with all work except pavement grooving substantially complete by September 24, 2027, and final completion within 120 days thereafter.
Construction Bid Source listed the project on October 15, 2026, under CBS ID 849025, describing the scope as rehabilitation of Runway 10L-28R and shoulders with mill-and-inlay paving, reconstruction of north shoulder pavement, blast pad sealing, NAVAID upgrades to Category II/III, taxiway rehabilitation and widening, construction of Taxiway A4 in a new location, and lighting, signage, drainage, markings, grading, and seeding. The notice states bonds and prevailing wages are required.
Construction Bid Source also includes a disclaimer that its notifications are compiled from various sources and updated daily, and that it does not assume responsibility for omissions or errors in the information provided.
Incentive payments range from $15,000 to $30,000 per day for early completion, capped at $235,000 if all work finishes before September 24, 2027, GovTribe reported.
The contract requires the contractor to perform at least 25 percent of the total contract cost with its own organization. Mobilization costs cannot exceed 10 percent of the total bid. Prevailing wage requirements apply under both Oregon law and the federal Davis-Bacon Act. The contractor must register with the Oregon Construction Contractors Board and comply with Disadvantaged Business Enterprise requirements and FAA Buy American preferences.