Texas has lifted a freeze on more than 1,800 data center projects, reversing a moratorium imposed in August. The move by outgoing Republican Governor Greg Abbott’s office comes as developers rush to secure approvals before Democratic Governor-elect Gina Hinojosa takes office in January and potentially enacts stricter rules.
Governor’s Office Reverses Course
Gov. Greg Abbott's office lifted a freeze on over 1,800 data center projects after ERCOT completed its data-gathering on local power impacts.
Outgoing Republican Governor Greg Abbott’s office lifted the freeze after the Electric Reliability Council of Texas (ERCOT) completed its data-gathering on data centers’ local impact, according to multiple reports. When the initial pause began in August, the office stated Abbott’s “top priority is to protect Texans’ safety and quality of life” due to concerns over power demands from new facilities.
The reversal halted 474 gigawatts of new power requests from being stuck under the moratorium. With the directive changed, developers are racing to secure permits before Democratic Governor-elect Gina Hinojosa takes office in January, having pledged to rein in construction and enact stricter state rules.
Developers Rush Before New Rules
Companies are rushing to get formal clearances before Gina Hinojosa’s January inauguration, as projects approved during this window may be grandfathered ahead of tougher regulations. A source from Tom’s Hardware said that the state had suspended 17 more construction permits in October before shutting down an automated approval portal.

Texas has restarted approvals for over 1,800 data center projects, a significant U-turn from a moratorium that put 474 gigawatts of new power requests on hold. The freeze was initially enacted in August, with the governor’s office stating that Abbott’s “top priority is to protect Texans’ safety and quality of life” amid concerns over the power required by new data centers.
The reversal follows the completion of an information-gathering process by the Electric Reliability Council of Texas (ERCOT), the state’s grid operator. Texas had further suspended 17 data center construction permits in October and shut down an automated approval portal that was still clearing new applications. With ERCOT’s investigation finished, the directive from Abbott’s office has permitted the resumption of processing.
Developers are rushing to file and lock in permits before Hinojosa’s January inauguration. During her campaign, Hinojosa pledged to rein in new data center construction and enact stricter state rules. Even with the freeze lifted, processing the 474 gigawatts of interconnection requests is not expected to be a quick process.
Developers Build Their Own Power
The slow processing of grid connections has pushed some developers to generate their own electricity on-site rather than wait.
They are taking advantage of Texas’s abundant natural gas supplies and a “lax” regulatory environment for gas turbines. This self-generation is a wider industry trend, exemplified by xAI installing eight converted jet engines to power a data center in Mississippi, a move with known health risks.
A National Issue
Data center growth and its impact on local grids and communities are not unique to Texas. Earlier this year, New York implemented a year-long ban on data center projects larger than 50 megawatts. In Northern Virginia, Amazon abandoned plans for four new data centers after public outcry, with the land now being repurposed for housing.
What to Watch Before January
The immediate focus is on how many of the 1,800-plus projects will receive formal clearances before Hinojosa takes office. Key questions include whether Texas will restore its automated permitting portal and what rules the new governor will bring.
Once in office, Hinojosa’s first move could be an executive freeze on pending reviews or new legislation addressing dedicated generation and ratepayer protections. The situation is further complicated by federal scrutiny, including a U.S. Senate bill that could raise the price of connecting to public utilities.