Whitmer Freezes Enbridge Line 5 Tunnel Permits After Michigan Supreme Court Ruling

Gov. Gretchen Whitmer ordered Michigan environmental regulators on Tuesday to halt work on the remaining state permits for Enbridge’s proposed Line 5 oil tunnel beneath the Straits of Mackinac, citing “significant delay and uncertainty” from a recent Michigan Supreme Court ruling.

  • Whitmer directed EGLE to suspend action on resource and wastewater permits for the four-mile tunnel.
  • The Michigan Supreme Court in July vacated a separate Public Service Commission permit and ordered a new review.
  • Enbridge spilled 1.3 million gallons of natural gas liquids in northern Wisconsin on Aug. 25, the largest such spill in state history.
  • Tribal nations and environmental groups have challenged the EGLE permits granted July 15.

The Michigan Supreme Court’s July decision in In re Application of Enbridge Energy to Replace and Relocate Line 5 found that the Public Service Commission should have considered certain environmental harms when it approved the tunnel in 2023, vacated that permit and remanded the matter for reconsideration, according to the governor’s office.

EGLE had issued its own water resource permits on July 15, but those were quickly challenged by four tribal nations and four environmental organizations. Whitmer said the high court’s ruling “introduces significant delay and uncertainty” and acknowledged the time Enbridge will need to seek a new MPSC permit.

Photo: michigan.gov

“This decision is not the finish line,” said Whitney Gravelle, president of the Bay Mills Indian Community. “Our responsibility to protect the Great Lakes does not end with a pause in permitting. Tribal Nations have been here since time immemorial, and we will be here long after any corporation has come and gone.”

David Gover, managing attorney for the Native American Rights Fund, said the tunnel poses risks to the Great Lakes and ancestral homelands. “It’s clear that Enbridge should abandon this failed project immediately,” he said.

Gov. Whitmer freezes state water permits for Enbridge's Line 5 tunnel project — My UP Now

Debbie Chizewer, managing attorney for Earthjustice, argued that a tunnel does not eliminate the threat. “Whether the oil pipeline is sitting in open water or encased in a tunnel, there is simply no good reason to continue pumping oil through the Great Lakes,” she said.

Enbridge said in a statement to Michigan Public that it had “worked to secure the approvals needed to relocate Line 5 from the open lakebed into a tunnel beneath the Straits of Mackinac” and that “both permitting rounds included detailed technical reviews, public meetings, hearings, and consideration of thousands of public comments.”

The company added that Line 5 “reliably and consistently serves the needs of Michigan and the Great Lakes region by delivering the energy people depend on every day” and that it remains “committed to that purpose and equally committed to safeguarding the Great Lakes.”

The proposed Line 5 tunnel is being delayed. The 70 year old Line 5 oil pipeline sits on the bottom of the Straits
Photo: michiganpublic.org

Whitmer has sought to shut down Line 5 since 2020, when she revoked the 1953 easement allowing the dual pipelines to cross the straits and ordered an orderly transition. The state continues to defend that authority in federal appellate court after a December 2025 ruling. The Great Lakes hold 21% of the world’s fresh surface water and supply drinking water for millions.