Wilmington Council Postpones Vote on 20-Year Water Deal for Amazon Data Center

“It just really seems like they’ve already made their minds up,” Wilmington resident Todd Barstow said, “no matter what is said or heard, that they’re going to push this through and approve it and let the development go through.”

Wilmington City Council postponed a vote on a 20-year water and sewer agreement for Amazon Data Services Inc.’s proposed 480-acre data center campus, delaying action until Dec. 4 after roughly 40 residents spoke in opposition on Nov. 25, datacenterdynamics.com reported.

Under the proposed agreement, the city would reserve 613,500 gallons of water per day — including 600,000 gallons for cooling and 13,500 gallons of potable water — and 305,000 gallons of daily sewer capacity. Amazon would pay standard consumption charges plus a capacity reservation fee to hold the allotment even when usage falls below the reserved amounts, WCPO reported.

The initial term runs 20 years with automatic one-year renewals unless Amazon provides notice of non-renewal. After completing its developer improvements, Amazon may terminate the services portion with 90 days’ written notice, freeing the reserved capacity for other customers.

Amazon’s infrastructure obligation is capped at $39.5 million, including up to $3 million for roadway improvements and $36.5 million for water and sewer upgrades such as thousands of feet of new lines, redundant connections and a 1-million-gallon water tower. Completed infrastructure would transfer to Wilmington, which would then assume long-term operation, maintenance and replacement responsibility, with a 12-month warranty period on accepted improvements.

Barstow, who lives near the planned campus, questioned what happens if costs exceed the cap. The agreement outlines options including scope reduction, additional funding or work suspension while funding is identified, rather than automatically requiring the city to cover overruns.

“Our fight’s not necessarily against data centers themselves or the positives that the city can get out of it,” Barstow told WCPO. “It’s really about where it’s at. It’s literally going to have buildings with these data halls and the generators within 500 feet of homes, single-family homes.”

Opposition has followed the project for months. Residents sued the city over the zoning process, alleging insufficient public notice. The Ohio Supreme Court blocked a citizen-led initiative from the November ballot in a 6–1 decision, ruling a provision allowing nearby residents to sue data center owners exceeded municipal authority.

An administrative appeal challenging the planning commission’s site-plan approval was filed Friday in Clinton County Court, Barstow said.

The postponed vote concerns Ordinance O-25-73, a compensation agreement among AWS, the city and the Clinton County Port Authority that includes tax exemptions for up to 30 years, datacenterdynamics.com reported.

AWS has said it will invest roughly $4 billion in the site off U.S. 68 at 1588 South U.S. 68, creating at least 100 permanent jobs with an $8 billion annual payroll and investing $25 million in public infrastructure.

Councilors plan to review documents and speak further with the community before the Dec. 4 meeting, when the Port Authority will be invited to address questions.