The Alaska Department of Environmental Conservation opened public comment Wednesday on a plan to dredge Auke Bay’s West Berth so larger ferries can keep serving Juneau while the East Berth undergoes repairs, Juneau Empire reported.
The state proposes removing about 11,000 cubic yards of sediment from a 1.5-acre area between Sept. 1 and Dec. 31, 2027. Only the East Berth can handle the Alaska Marine Highway System’s larger vessels, and it is nearing the end of its useful life, according to an environmental evaluation filed with the request. Dredging the West Berth would allow service to continue during the East Berth closure, though the state has said schedules may change.
Sediment testing is still underway. A January 2025 environmental assessment classified the dredge area as moderate risk, citing past petroleum spills, nearby fuel operations and runoff from 14 stormwater outlets. DEC’s database listed 111 spills to the water at Auke Bay from 2008 through the January 2025 review, nearly all reported as sheens from vessels in the bay or harbor, alaskanews.com reported. In 2003, crews removing two underground fuel tanks dug out about 13 cubic yards of contaminated soil; diesel remained in the soil because buried utility lines and wet conditions prevented further excavation.
If testing finds the sediment too contaminated for offshore disposal, it would be transported in sealed containers to a permitted upland site.
Otherwise, it would be barged about a mile to a previously used disposal area on state-owned submerged land. The offshore site was moved after an Alaska Department of Fish and Game biologist warned the original location was high-value red king crab habitat. Fish and Game advised dredging from September through December, when larger crabs have typically migrated to deeper water, and vessels would be capped at 10 knots to protect marine mammals, with operations halting if animals approach.
The dredge area sits less than 200 feet from the Auk Nu Cove Conservation Easement, a protected estuary that the Southeast Alaska Land Trust says holds nearly 5 acres of eelgrass beds. The U.S. Army Corps of Engineers is taking comment through Dec. 14 but cannot issue its permit until DEC certifies or waives its water quality review.
Comments on the DEC review are due Dec. 18, referencing public notice POA-2026-00227.
The project has been delayed before. A 2022 state notice described construction as early as fall 2024, and last year NOAA reissued a federal permit covering pile-driving noise that could affect whales, saying “none of the work” had been done.