Applied Digital announced on November 24 that it has completed base-build commissioning for the first 75 megawatts of its initial 150-megawatt data center building at Polaris Forge 2 in Harwood, North Dakota, and achieved Ready for Service for the first 25-megawatt data hall on schedule, the company said.
The milestone marks the first Ready for Service achievement at the company’s second AI Factory campus, following the delivery of 250 MW of operational critical IT load at Polaris Forge 1 in Ellendale, North Dakota, the company said. With base-build infrastructure for the full 75 MW phase tested and commissioned, the remaining 50 MW can now advance through fit-out and customer delivery.
Hyperscaler lease anchors campus
Every 150 MW building at the AI Factory Campus is brought online in two 75 MW stages, with three 25 MW data halls tested and commissioned simultaneously in each stage, the company said. The Polaris Forge 2 data center campus is largely leased by an unnamed investment-grade hyperscaler, which signed a 15-year 200MW lease in October 2025, and has right of first refusal on up to 800MW more capacity at the site.
Execution model tested across campuses
“AI infrastructure demand is not theoretical for us. It’s backed by long-term customer commitments, and our focus is on delivering against them,” said Wes Cummins, Chairman and Chief Executive Officer of Applied Digital.
“With our second campus now reaching Ready for Service on schedule, we’re demonstrating that our execution model is repeatable. The ability to consistently turn contracted demand into delivered AI capacity is what will define the leaders in this industry, and that’s exactly what we’re doing at Applied Digital.”

Hyperscaler lease and portfolio growth
Plans for the campus were first announced in August 2025, and the site is ultimately set to offer 1 GW across 900 acres, the same outlet said.
Earlier this week Applied Digital disclosed an 18-year capacity agreement with another investment-grade hyperscaler carrying a base-term revenue of $5.4 billion that could reach $12.7 billion if all renewal options are exercised over a potential 33 years, Datacenter Dynamics reported.
That deal lifted the company’s total contracted base-term revenue to more than $41 billion, and to $100 billion if all renewal options are exercised, the outlet said. Applied Digital’s portfolio now exceeds 1.6 GW of total contracted critical IT load and 2.2 GW of grid-connected peak load, according to Datacenter Dynamics.
Power infrastructure progress and delivery timeline
The filing gave no date for final energization.
Applied Digital’s second campus reaching Ready for Service on schedule demonstrates that the execution model Wes Cummins has honed as Chairman and Chief Executive Officer since co-founding the company is repeatable, he said in the November 24 announcement.
His more than 20 years of experience as a technology investor, including leading technology investing at Nokomis Capital and founding 272 Capital LP as CEO, provided the capital-markets foundation for turning contracted demand into delivered AI capacity across multiple campuses.
Power infrastructure and next steps
Minnkota Power Cooperative oversaw design and construction of more than 1.5 miles of 345-kilovolt transmission line and the new Agassiz substation, with Burns & McDonnell serving as engineering, procurement and construction contractor.
Applied Digital executive vice president for external affairs Nick Phillips put the company’s investment in regional electrical upgrades through Agassiz at $112 million in an October 28 account published by Minnkota, Infraday reported. A Minnkota construction report filed November 23 with the North Dakota Public Service Commission showed transmission foundations complete with structures set and conductors strung, while substation equipment installation reached 80% and testing and commissioning reached 15% as of October.
The filing gave no date for final energization.
Infraday reported that the November 24 announcement gave no handover date for the remaining two halls and did not say whether the customer would take them together. The company previously projected full capacity at Harwood in early 2027, Infraday reported, with management expecting initial operations at Harwood to bring delivered capacity across its North Dakota campuses to 300 MW by year-end.