Aurora City Council unanimously passed a temporary moratorium on new data centers Monday, halting development across most of the city through September 2027 while officials draft permanent land-use rules.
- The moratorium covers land west and south of the intersection of Powhaton Road and Interstate 70.
- Vantage Data Centers abandoned its controversial Trident campus site on East 48th Avenue the same day.
- Council is drafting residential setbacks of 750 feet and noise-study requirements for future projects.
Trident developer withdraws site plan
Vantage Data Centers announced Monday it would no longer pursue the Trident data center site adjacent to the Windler, Green Valley Ranch and Reserve neighborhoods. The project had drawn months of opposition over potential environmental and health impacts.
“While we will no longer pursue the current site for our proposed campus, Vantage remains committed to being a responsible long-term partner in the state,” Misty Allen, vice president of public policy in North America for Vantage, said in a statement reported by Sentinel Colorado.
City officials learned of the withdrawal as the council meeting began. “Neither City Manager Jason Batchelor, City Attorney Pete Schulte nor other members of the city team were aware of that news until it was reported by various outlets near the start of the meeting,” a city spokesperson told CBS News Colorado.
Mayor hails community organizing
Mayor Mike Coffman, who cast a tie-breaking vote against a moratorium in August, credited neighbors for the reversal.
“I’m just grateful that the nightmare is over with and that you prevailed,” Coffman told the audience. He added that home values near the proposed Trident site “would have sunk like a rock” if the project had proceeded, The Center Square reported.
Council split on scope and messaging
The moratorium passed 10-0 with Councilmember Curtis Gardner excused. But members disagreed on the measure’s reach and framing.
Councilmember Stephanie Hancock, who opposed previous moratoriums, supported this compromise but objected to the term.
“I’m not in favor of the word moratorium, that really bothers me and I think it sends a weird message to businesses,” Hancock said.
“Data centers are here to stay… regardless of whether the public likes it or not, data centers are a national security matter,” she added, drawing jeers from the crowd, The Center Square reported.
Councilmember Alli Jackson voted for the pause but said it did not go far enough.
“I do have a hard time voting on this because when I listen to the community… they don’t want data centers in Aurora, period,” Jackson told Sentinel Colorado. “Pollution doesn’t care about (zoning).”

Permanent regulations in development
The moratorium expires September 30, 2027, or earlier if council adopts permanent rules. Staff is drafting an ordinance that would prohibit data centers within 750 feet of residentially zoned land and require a conditional-use permit for sites between 750 feet and a half-mile from homes, Sentinel Colorado reported. Councilmember Amy Wiles said she is also exploring rules on vibrations, low-frequency noise and community benefit agreements.
Councilmember Angela Lawson noted the Colorado legislature is expected to introduce several data-center bills in the upcoming session.
Labor representatives opposed the pause. Chaz Tedesco, speaking for a local union, said at the meeting that Aurora “should not have to choose between protecting neighborhoods and supporting jobs,” according to Sentinel Colorado.
Aurora joins Fort Collins and Littleton, which enacted six-month data center moratoriums earlier this month, The Center Square reported.