Juneau is asking developers to take a crack at one of the most difficult building sites in Alaska, offering up a steep, historic downtown hillside and a package of subsidies that still might not make the math work.
The City and Borough of Juneau published a request for qualifications Thursday for the Telephone Hill redevelopment, a 1.78-acre parcel sandwiched between the State Office Building and Egan Drive where the city hopes to see up to 155 housing units rise, CBJ announced. The solicitation closes February 11, 2027, with the Assembly slated to review responses at a public meeting in March 2027.
“The intent of this Request for Qualifications is to make the response process as straightforward as possible in order to encourage submittals from the most capable and best-qualified developers,” CBJ said in the solicitation, the Juneau Empire reported. The city is not asking for designs or financial models yet — just proof that a team has handled comparable urban infill and public-private partnerships.
“From what I know, the proposed development on Telephone Hill of 155 units with 25 affordable is not financially feasible,”
The numbers that scare developers
A 2024 market analysis commissioned by the city found no version of the project that breaks even. For a building split 80% market-rate and 20% affordable with no new parking, the study calculated a gap of $68,000 to $137,000 per unit depending on construction costs — even after a 12-year property tax exemption worth roughly 80%, Alaska News reported. The city’s affordable housing fund has historically contributed about $50,000 per unit.
The RFQ acknowledges “feasibility challenges” from the site’s slopes, the high cost of borrowing, and the likelihood of buried heating-oil tanks. Scoring criteria make the reality plain: past project quality counts for 45 points, team experience for 25, and vision for the site just 30. Projects “requiring less CBJ subsidies will score higher,” the solicitation says.
What the city is putting on the table
To close the gap, CBJ is offering a menu of incentives: cash for demolition and site work, that 12-year tax abatement, grants or loans up to $50,000 per unit from the housing fund, and a land price described as “potentially negotiable or deferred.”
The Assembly set aside $5.5 million in 2025 for demolition and site prep, including $2 million voters approved via the 1% sales tax in 2022. In April, the Assembly paused demolition bids until a developer delivers site-specific plans.
Any team that taps the housing fund must make 20% of units — 31 of 155 — affordable to households earning 80% of area median income for at least 10 years or the life of the loan. Units supported by the fund or the tax break cannot become short-term rentals.
History, opposition, and an open question
Seven houses sit on the hill today, built between 1882 and 1939. The oldest was Juneau’s longest continuously occupied home until its last resident left in March. The Alaska Historical Association has applied to list Telephone Hill as a national historic district; the city’s Historic Resources Advisory Committee voted 6-0 in October to support the nomination. Listing alone would not block demolition unless federal money enters the picture.
The state bought the hill in 1971 for offices and once envisioned a new Capitol there. It declared the land surplus in 2019 and conveyed it to the city in 2022. Since then, residents have testified repeatedly at Assembly meetings urging a pause, a return to private ownership, or preservation of the existing homes.
The City and Borough of Juneau formed on July 1, 1970, when the City of Juneau merged with the City of Douglas and the Greater Juneau Borough, creating a consolidated municipality that ranks as the second-largest in the United States by area — larger than Rhode Island and Delaware.
It became the capital of Alaska in 1906, after the seat of government moved from Sitka, and remains the only U.S. state capital on the mainland without road access to the rest of the continent.
Whoever is selected must agree to an “open book” process, letting the city audit project finances to ensure “no inappropriate windfall profit arising from public property.” An optional pre-solicitation conference and site tour is scheduled for December 17; registration closes December 16.