Dublin’s Merrion Square Tea Room Delayed to Summer 2027 as Costs Top €6m

Dublin City Council confirmed on Monday that the Merrion Square tea rooms will not open until May or June 2027, nearly three years past the original deadline.

  • Project budget has risen from €2.4m in 2018 to over €6m
  • Building footprint reduced by 20% from 371 sq.m to 292 sq.m
  • Contractor Bracegrade delayed 18 months by contractual dispute
  • External review of cost overruns and governance now underway

Costs triple since 2018 estimate

The facility, in development since 2015, was budgeted at €2.4 million in 2018. Dublin City Council now puts the cost at more than €6 million, though it earlier warned the bill could reach €7.5 million. The council said the increase reflects the “cumulative impact of Covid, extended programme duration, construction inflation, statutory compliance requirements, contractual disputes and associated delay costs over the period of the project”, RTÉ reported.

Design fees under scrutiny

Architects Bucholz McEvoy’s fees grew from €246,000 in 2015 to €655,000 in recent years, a rise flagged by the Local Government Audit Service in its 2024 audit of DCC. The council said the fee was “broadly in line with current industry design team fees scale for a building of this value and complexity”, but acknowledged the project did not fully comply with procurement regulations.

Photo: globeverge.com

Documents released under Freedom of Information show the council’s Corporate Project Governance Board suspended the project in 2019 over scope and cost concerns, Fine Gael Councillor Danny Byrne said. It was restarted the following year. “Seven years ago, the council’s own governance board was questioning the costs and the business case. Seven years later I’m still looking for answers”, Byrne told RTÉ.

Contractor dispute delayed work 18 months

Main contractor Bracegrade was delayed by 18 months due to a contractual dispute. Work resumed earlier this year following mediation with the contractor and the design team. “The contractor has provided a date of March/April 2027 for the completion of construction and fit out works. It is anticipated that the operator could have the pavilion open to the public in May/June 2027”, the council said in a statement to RTÉ.

Why are Merrion Square’s €6m-plus tea rooms still not open? — RTÉ News

Councillors split on value

Independent Councillor Mannix Flynn called it “the most expensive tea room in the history of the State”, arguing the money should go to housing. “We’re not in a crisis of tea, we’re in a crisis of housing and while I can’t get a window fixed in a block of flats, Dublin City Council seems to be able to come up willy-nilly with millions for unnecessary tea rooms”, he said.

Byrne called the project excessive: “It’s huge money for a tea room, a public toilet and some artist space”. He said councillors supported the building at planning stage but not “runaway costs”, adding “there seems to be a disregard for the taxpayers’ money”.

Donough Cahill, Executive Director of the Irish Georgian Society, defended the ambition: “Merrion Square is one of the great architectural set pieces of Georgian Dublin and its park is the heart of the square”. He said “trying to achieve that standard of excellence is something that’s very understandable”, provided the building “touch the ground lightly”.

External review announced

The council said it will appoint an external consultant to review the “extent and causes of cost overruns and schedule delays” and examine the “effectiveness of project governance, reporting and decision-making arrangements”, members were told on Monday.