Highgate Falls Hydroelectric Project environmental review findings were released by the Federal Energy Regulatory Commission, Federal Register reported.
An Environmental Assessment was formulated by the Office of Energy Projects following their evaluation of the license application for the undertaking situated on the Missisquoi River within the Town of Highgate, Franklin County, Vermont.
The Environmental Assessment contains staff analysis of potential environmental impacts and concludes that licensing the project with appropriate environmental protective measures would not constitute a major federal action significantly affecting the quality of the human environment.
Public comments on the environmental assessment must be filed by 5:00 p.m. Eastern Time on December 14, 2026.
The Commission strongly encourages electronic filing using the Commission eFiling system. Commenters can submit brief comments up to 10,000 characters without prior registration through the QuickComment system.
For assistance, contact FERC Online Support at [email protected], (866) 208-3676, or (202) 502-8659.

Paper copies sent via the U.S. Postal Service must be addressed to Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing must include docket number P-2547-095.
Reach out to the Office of Public Participation by calling (202) 502-6595 or writing to [email protected] for public inquiries and help regarding submissions like interventions, comments, or requests for rehearing.
Pursuant to 18 CFR 2.1 authority dated November 13, 2026, details can be obtained by reaching out to Arash Barsari via email at [email protected] or by calling (202) 502-6207.