Four Seasons Breaks Ground in Charleston Historic District

  • Construction began Nov. 19 at 155 Meeting Street after February demolition of the Days Inn.
  • 139 hotel rooms and 36 private residences priced from $5 million across three buildings.
  • Developer Strategic Property Partners is owned by Bill Gates’ Cascade Investment, which spent $57 million assembling the 1.9-acre site.
  • Completion now targeted for 2030, two years later than the original 2028 estimate.

Developers, city officials and tourism leaders gathered Nov. 19 for the ceremonial start of construction at the former Days Inn site, The Post and Courier reported.

The motor lodge, a 121-room horseshoe-shaped property on Horlbeck Alley, was demolished beginning Feb. 19 after months of archaeological excavation by Brockington and Associates to document historic elements beneath the surface.

“We’re unapologetic about the high standards that we want and we demand in Charleston,” Mayor William Cogswell said at the ceremony.

“I think the Four Seasons is going to be better for it.”

Josh Taube, chief executive officer of Strategic Property Partners, called the milestone “the culmination of years of planning, collaboration and dedication from our teams and partners,” according to HotelsMag.com. Brad Cooke, the firm’s executive vice president of development, added that reaching the construction phase “is a testament to the dedication and collaboration of our entire project team.”

Cascade Investment controls the project

Bill Gates’ Cascade Investment LLC began acquiring the Days Inn and neighboring downtown properties in late 2022, eventually spending $57 million on the real estate, Markets of Tomorrow reported. Cascade owns Strategic Property Partners and is the controlling shareholder of Four Seasons Hotels and Resorts, aligning the developer, landowner and brand under single ownership.

The deal went from assembling parcels to a public announcement in June 2025. An earlier design that placed an above-ground parking garage inside the tallest building was revised in March 2025, removing the garage and adding more hotel rooms and residences within the height and density limits the city had already approved.

Three buildings, eight stories, strict review

The development spans three buildings totaling roughly 160,000 square feet on 1.9 acres, with the tallest rising eight stories. Morris Adjmi Architects leads architecture and residence interiors; Lark Design Studios handles hotel interiors; Hollander Design is responsible for landscape. All three firms are based in New York. The Historic District’s Board of Architectural Review limits demolition, height and design changes, keeping new supply scarce.

Photo: hotelsmag.com

Residences start at $5 million with hotel services

Owners receive a private entrance, dedicated Director of Residences, and Four Seasons-staffed property management providing in-residence dining, housekeeping and concierge. Many units include balconies or terraces with downtown skyline views. The developer said it has fielded thousands of inquiries since marketing began, many from regional buyers. Four Seasons operates a global portfolio of 135 hotels.

Mayor and tourism leaders welcome the project

Mayor William Cogswell praised Charleston’s architectural review process at the Nov. 19 groundbreaking, saying the city is “unapologetic about the high standards that we want and we demand,” The Post and Courier reported. He added that the Four Seasons would be better for those standards and that the project would bring construction and hospitality jobs to the heart of downtown.

Helen Hill, president and CEO of Explore Charleston, said the development will change local and statewide hospitality, according to The Post and Courier. She described the Four Seasons brand as globally renowned for exceptional service and said the project will capture the essence of Charleston while complementing the city’s existing collection of world-class accommodations.

Timeline shifts from 2028 to 2030

The Post and Courier attributed the delay to demolition setbacks and the time needed to select a contractor.

BINYAN_SPP3330_FourSeasons_Charleston_S055_EXT_SouthEastcorner_Aerial_Final3500.jpg (Copy)
Photo: postandcourier.com

Construction timeline shifts to 2030 target

Hoar Construction serves as general contractor with Charleston-based Iskagna as owner’s representative. Excavation is expected to begin after Thanksgiving. Horlbeck Alley is reduced to one lane with detours posted for cars, pedestrians and carriage tours. The project’s targeted completion has shifted.

When Four Seasons announced the Charleston plans in June 2025, the hotel was expected to open in 2028. Recent reporting places the target in 2030, though the developer’s website continues to display a 2029 date, What’s Going On In Charleston noted. Strategic Property Partners says more updates are coming in the weeks ahead.