The Huntsville Water Commission learned Nov. 19 that the city’s $7.5 million wastewater plant upgrade will finish in March, roughly four months past the original December target, Madison County Record reported.
Executive Director Sean Davis told commissioners a contractor backlog caused the delay. Switching vendors would add $140,000 and might not change the timetable, he said. State officials have accepted the revised schedule. “They’re OK with that,” Davis said.
The commission also approved selling a 2001 Vac-Con sewer truck for $27,500 through the state surplus site, below the $30,000 reserve. “For the age of our truck, that’s a good [selling] price,” Davis said. Commissioner Jared Rogers moved to accept the bid; Commissioner Preston Scott seconded. The motion passed.
Distribution Manager Tye Rudolph said crews installed a 6-inch water line on Northcross and plan to take samples. Davis said the upgrade provides fire protection for an area where eight duplexes are under construction.
Davis said the 2025 audit was certified and submitted to the state. In a year-end project review, he noted $6,475 spent on geographic information system mapping, with staff adding data as time allows. The Cain Street lift station design cost $29,696.25, just under its $30,000 budget, with on-site work scheduled for 2027.
The utility has spent $64,454.93 on the $700,000 sewer trunk line design, slated for third-quarter 2027 completion.
A $119,000 dryer scrubber for odor control could come in under budget, Davis said, with installation also planned for third-quarter 2027. Survey and design are underway for a $345,500 airport storage tank project, covered by a $3 million federal grant from the Department of Housing and Urban Development. No invoices have been received yet.
The commission’s next meeting is set for noon Thursday, Dec. 17, at the Basham Building.