Interstate 285 southbound lanes shut down Saturday afternoon after a bridge crossing the Chattahoochee River separated in Smyrna, FOX 5 Atlanta reported.
The emergency closure began around 4:25 p.m. when the Georgia Department of Transportation diverted all southbound traffic at State Route 280/South Cobb Drive. Smyrna police initially reported the separation, prompting an immediate response from state transportation officials to secure the span.
While the sudden closure disrupted weekend travel, state officials worked to stabilize the area through the evening. After crews inspected the bridge, they were able to reopen multiple lanes, though two right lanes remained blocked for emergency maintenance.
“While there is no structural danger to the bridge, the issue has potential to impact ride quality for motorists,” GDOT said in a statement released Saturday night.
The disruption follows a pattern of heavy construction along the Cobb and Fulton County line. Drivers in the area faced this sudden emergency and a massive, pre-planned preservation project occurring just a few miles away.
I-285 Lane Closures

| Location | Direction | Status |
|---|---|---|
| South Cobb Drive | Southbound | Emergency closure; partial reopening |
| Powers Ferry Road/Northside Drive | Eastbound | Three right lanes closed for scheduled work |
For those traveling the southbound lanes in Smyrna, contractors began making temporary repairs on Saturday night. Officials expect all southbound lanes to reopen no later than 10 p.m. A more permanent, long-term fix is scheduled to begin in early December.
The immediate impact falls heavily on commuters and logistics providers who rely on the I-285 corridor to move goods and people between North Atlanta and the surrounding suburbs. When a primary artery like the Chattahoochee River crossing fails, the resulting congestion spills into local surface streets like South Cobb Drive, slowing down local commerce and emergency response times.
Drivers are encouraged to check real-time conditions via the Georgia 511 website or mobile app to avoid the heaviest delays. Officials urge motorists to reduce their speed and exercise caution when passing through active work zones.
Contractors are scheduled to begin a long-term fix in early December.