Jindal Energy (Botswana) executed an eight-year loan of about $500 million with three Indian banks, leaving roughly $500 million still to raise toward a $1 billion financing target for its Mmamabula coal-fired power plant, Business Insider Africa reported.
The lenders are Axis Bank, ICICI Bank and Export-Import Bank of India, according to a November 17 announcement by JSA Advocates & Solicitors, which advised the project company. JSA said the financing supports phases I and II of the greenfield thermal plant and that the remaining $500 million is expected in the coming months.
A November 17 release from JSA Advocates & Solicitors said about $500 million had been arranged with documents for an eight-year first phase executed by a consortium that included Axis Bank, ICICI Bank and Exim Bank alongside other Indian lenders.
Bloomberg, citing people familiar with the matter, put a separate loan at about $470 million and described it as a nine-year facility. The November 17 legal announcement gives an approximate $500 million amount and an eight-year term. It remains unclear from public disclosures whether these descriptions refer to the same facility or different stages of the financing.
Botswana Power Corporation lists Jindal’s commitment as two 300-megawatt coal plants under power-purchase agreements. Jindal’s project website describes a 700-megawatt net plant with a December 2026 commissioning target. The 2026 budget for Botswana refers to a 600-megawatt Mmamabula plant, with the first 150 megawatts expected by December 2026 and full capacity by June 2029. The public figures and timelines differ, and the available disclosures do not reconcile them.

JSA Advocates & Solicitors advised Jindal Power on the transaction, leading a team that included partners Karan Mitroo and Ankita Parasar and principal associates Samarth Sharma and Surbhi Jain, Bar and Bench said. JSA also undertook a detailed analysis of Phase II financing terms to ensure parity with Phase I terms, the publication added.
Desai Law Group and Erriah Law Chambers acted as international counsel to Jindal Energy, Law.asia added.
Bloomberg, citing people familiar with the matter, reported a separate offshore loan of about $470 million from a consortium of three Indian lenders — Axis Bank, ICICI Bank and Export-Import Bank of India — as a nine-year facility priced at roughly 300 to 325 basis points over the Secured Overnight Financing Rate, Power Technology said.
The plant is intended to supply Botswana’s domestic demand and export surplus electricity to regional markets, the publication added.

Botswana’s minerals and energy minister told Parliament in March that electricity demand was growing about 5 percent a year and that imports and rotational load-shedding would continue until new generation projects came online. Botswana’s budget outlines plans to add 1.5 gigawatts of renewable energy by the first quarter of 2027. The Jindal project is one part of that mix, with BPC as its proposed buyer.
“The underlying project is itself a landmark undertaking, representing the only fossil fuel-based power plant that Botswana plans to procure in the next 20 years, underscoring its strategic importance to the country’s energy security,” said Anurag Dwivedi, partner at JSA Advocates & Solicitors, describing a two-tier security structure using a trust and a special purpose vehicle to address enforcement challenges in Botswana.