Michigan Gov. Whitmer Halts Permits for Enbridge Line 5 Tunnel Project

Michigan Governor Gretchen Whitmer has ordered a halt to state permitting for the Enbridge Line 5 tunnel project.

Whitmer directed the state Department of Environment, Great Lakes and Energy (EGLE) to suspend further action on resource and wastewater permits for the proposed four-mile tunnel beneath the Straits of Mackinac, the governor’s office reported.

  • Gov. Whitmer ordered EGLE to suspend Line 5 tunnel permits on Nov. 24, 2026.
  • The Michigan Supreme Court vacated project approval on July 31, 2026.
  • Enbridge’s twin underwater Line 5 pipelines are 73 years old.

The move follows a Michigan Supreme Court decision on July 31 that vacated state siting approval for the project, ENR reported. The court found the Michigan Public Service Commission had not properly applied the Michigan Environmental Protection Act in reviewing the proposed replacement segment. “Just one spill threatens irreparable damage to our water, our economy and our way of life.”

The directive acknowledges the significant delay and uncertainty introduced by the court’s ruling, including the time Enbridge would need to seek renewed approval from the Michigan Public Service Commission, ENR reported. “They also involved extensive interaction between Michigan’s tribal leaders and state agencies.”

A federal court ruled in December 2025 that Michigan could not enforce its order to shut down the existing Line 5 pipelines. The state is appealing that decision, ENR reported. In July, EGLE granted water resource permits to Enbridge that were quickly challenged by four Tribal Nations and four environmental organizations.

The governor’s announcement suspends further action on those permits. Enbridge has also faced other setbacks related to the Line 5 pipeline. In August, an unoccupied subcontractor’s flatbed truck rolled into an open excavation near Saxon, Wis., striking a valve and causing the release of about 1.3 million gallons of natural gas liquids, ENR reported. Earthjustice noted this was the largest such spill in state history. Enbridge estimates costs related to the accident at about $15.1 million.

The company is building a 41-mile, 30-inch diameter section to bypass the Bad River Band tribal land, ENR reported. Benson has said she would explore all options to protect the Great Lakes and advocated for a statewide audit of aging pipelines including Line 5, ENR reported.

The state and Enbridge remain in a stalemate as the twin spans continue to pump thousands of barrels of light crude oil a day along the lake bottom.

Enbridge operates North America’s longest pipeline system, with a crude oil network spanning 28,661 kilometres (17,809 miles) and a natural gas system extending 38,300 kilometres (23,800 miles) across Canada, the United States and the Gulf of Mexico.

The company’s safety record includes the 2010 Kalamazoo River spill in Michigan — one of the largest inland oil spills in U.S. history — and the Line 3 spill in Minnesota, which stands as the largest inland oil spill in the United States.