Minneapolis has paused a $5 million flood‑mitigation project near Lake Harriet after residents reported damage to century‑old homes, sidewalks, trees and a retaining wall, Startribune reported.
The Oliver Avenue South project in the Lynnhurst neighborhood was designed to replace undersized storm sewer pipes and install a large underground box culvert for stormwater storage. It is one piece of a $59 million citywide flood‑mitigation program. Construction began this year and was slated to run through summer 2027, but by August the city had halted work and launched a “construction feasibility review,” city spokesman Allen Henry said.
Residents said the contractor, Geislinger & Sons, encountered sandy soil that made excavation unstable. “It was like digging a hole in a sandbox,” neighbors told Startribune. When crews tried to shore the trench with support beams, vibrations cracked plaster, shifted foundations, and caused doors and windows to stick in homes up to 104 years old. One homeowner documented more than 150 cracks in interior plaster; a retaining wall slid several inches; sidewalks and the boulevard were undermined.
Jenny Porter, who lives on the block, said when construction started, the hole was getting bigger and bigger and bigger. It was collapsing on the sides and destabilizing the boulevard and undermining the sidewalks.
Homeowners warned the city about the soil before construction started. The city promised soil borings, but residents said the work proceeded without adequate preparation. When damage appeared, they were directed to file claims with the contractor’s insurer. “The sidewalks are collapsing. We’re damaging homes. And the city’s response was, ‘Well, you can make a claim with the construction company,’” Porter said.
City Council Member Linea Palmisano, who represents the ward, wrote to constituents that she was “unhappy with the way the project transpired” and believes the city “has an obligation to do better by residents,” citing a lack of engagement. She said her “insistent urging” helped halt the project, and that the city may “seriously reduc[e] the scope of the project or choos[e] not to move forward with it at all.” About a week later, city leaders told her some sewer work would still be needed, even if smaller.
Trevor Porter, an engineering director and Jenny Porter’s husband, said he submitted 10 public records requests for project details, vibration limits, tree‑loss data and the engineer who signed off on the design.
As of late October, nine had been pending for 76 days. “If a neighborhood with those resources struggled to obtain information and influence project direction, what happens in neighborhoods that do not possess the same advantages?” he asked.
The city and Geislinger & Sons mutually agreed to terminate the contract “as work on the project was exceeding the scope of the contract,” Henry said.
The street has been restored for winter. A message left with Geislinger & Sons was not immediately returned.
The city later hired a public‑relations firm to manage communications. Dave Keepper, an advertising writer on Oliver Avenue, said it seemed like the neighborhood was being managed and handled rather than engaged and listened to. He called the project a “colossal waste of money.”