Massachusetts School Building Authority project data was last updated for the August 27, 2025 board meeting.

The MSBA publishes a Capital Planning Overview Report, Capital Pipeline Status Chart, Estimated Bid Schedule and Consultant/Contractor Status Report to track projects from Eligibility Period through Final Audit Approved. Each document carries the same notation: updated for the August 27, 2025 board meeting.

Pipeline tracking stalled

The Capital Pipeline Status Chart provides the status of Statements of Interest categorized in the MSBA’s Capital Pipeline. The Estimated Bid Schedule covers completed and upcoming bid packages for 2024 through 2026, with dates marked as estimates only.

The Consultant/Contractor Status Report lists district, prioritized school, SOI status, owner’s project manager, designer, commissioning agent, construction procurement status and construction manager at risk or general contractor where available.

All four reports note that information has not been provided for some districts in “audit” and “complete” status categories.

Interactive bid map available

The map does not carry a specific update date.

Documents note incomplete district data

The MSBA says the Consultant/Contractor Status Report and other capital planning documents lack information for some of the districts in the “audit” and “complete” status categories.

Source 2 shows the missing data applies to the Consultant/Contractor Status Report, which tracks district, prioritized school, SOI status, owner’s project manager, designer, commissioning agent, construction procurement status and construction manager at risk or general contractor where available.

Source 2 describes the map as covering all MSBA projects approved for Preferred Schematic Design, while the Estimated Bid Schedule covers completed and upcoming bid packages for 2024 through 2026 with dates marked as estimates only.

Next board meeting unscheduled

The MSBA has not announced when the next board meeting will occur or when the capital planning documents will be refreshed.