The new Iowa 9/WIS 82 Mississippi River Bridge opened to traffic on November 6, 2026, marking the completion of a major infrastructure project months ahead of the original spring 2027 schedule. The $165 million project began in late 2023.
- The $165 million project replaces the historic Black Hawk Bridge, which permanently closed in late 2025.
- The new structure sits on foundations 150 feet deep, nearly three times the depth of the 1931 original.
- Construction required 11,400 cubic yards of concrete and 6,600 tons of steel.
- The crossing is expected to carry approximately 2,500 vehicles daily.
Collaboration Across State Lines
The ribbon-cutting ceremony featured officials from both states, including Iowa Department of Transportation Director Scott Marler and Wisconsin Governor Tony Evers, who highlighted the regional significance of the connection.
“The opening of the new Lansing Bridge is a major achievement for Wisconsin and our partners in Iowa, and it shows just what we can accomplish when we work across state lines to make life easier for our states’ residents, businesses, and visitors,” Evers said, according to wkow.com.
“This project reflects our commitment to building the 21st-century infrastructure needed to support a 21st-century economy, and I’m proud of the collaboration and work done to restore this vital connection between our states as quickly and as safely as possible, ensuring a reliable connection for the region for generations to come.”
The project, which began in late 2023, required the cooperation of more than 60 contractors and consultants. To maintain the link between Lansing and Crawford County during the construction period, the Iowa and Wisconsin Departments of Transportation funded a car ferry service that transported more than 160,000 vehicles, wkow.com reported.
“On behalf of Iowa Governor Kim Reynolds, we want to express our gratitude to all the project personnel who made extraordinary efforts to open this bridge early, and we thank everyone in Iowa and Wisconsin for patience and perseverance,” Marler said, as noted by iowadot.gov.
Opening ceremony marks bridge debut
“What a great day,” proclaimed Iowa DOT Director Scott Marler, as reported by iowadot.gov.
Ferry service bridged communities during closure
After the historic Black Hawk Bridge closed permanently in late 2025 following temporary shutdowns earlier that year and in 2024, WisDOT and the Iowa DOT partnered to provide free temporary car ferry service starting in November 2025, WXOW reported.
Motorists unable or unwilling to use the ferry traveled a detour through Marquette, Iowa, and Prairie du Chien, Wisconsin, roughly 30 miles south of the Lansing crossing, according to iowadot.gov.
The original Black Hawk Bridge, a riveted cantilever through truss completed in 1931 under designer and chief engineer Melvin B. Stone with trusses erected by the McClintic-Marshall Company of Chicago using Inland Steel Company steel, served as the northernmost Mississippi River crossing in Iowa.
Originally a privately owned toll bridge operated by the Iowa-Wisconsin Bridge Company, it closed from 1945 to 1957 after ice damming damage bankrupted the company, prompting the two states to acquire and repair it.

Ongoing Work and Future Access
While the bridge is now open to regular traffic, the project is not yet fully concluded. Crews will remain on-site through the winter to finalize the removal of the old bridge piers and foundations, as well as the restoration of the former ferry landing areas.
Additional deck work is planned for the spring of 2027, which will cause traffic disruptions but is not expected to require a full closure of the crossing. Travelers can monitor the latest status of the route through the state’s 511 system, iowadot.gov reported. The entire project is slated for completion in late spring 2027.