Newfoundland and Labrador’s Public Utilities Board approved $806.8 million for a new combustion turbine plant on Friday, cutting $189.1 million from the utility’s latest request.
The board said it is satisfied the Avalon Combustion Turbine project is necessary for the island’s electricity grid, CBC reported. The decision authorizes three new turbines with a total nominal capacity of 150 megawatts, synchronous condenser capability, a new powerhouse, raw water system, fuel offloading system and adjustments to transmission facilities at the existing Holyrood site. It is the largest capital expenditure the PUB has ever approved.
Budget cut from near $1 billion
Newfoundland and Labrador Hydro pegged the cost at $891.4 million in March 2025, then raised the estimate to $995.5 million this year, citing increasing global demand for combustion turbines related to data centers. If Hydro needs more money, it must seek approval from the PUB first.
Resource study drives turbine decision
Hydro identified the need for additional generation through its recent Resource Adequacy Study Review to meet system reliability requirements, the utility stated. The study determined that adding a combustion turbine at Holyrood was one of the least-cost and environmentally responsible options to maintain compliance with Canada’s draft Clean Electricity Regulations.
The new unit is expected to add 150 megawatts of capacity for peaking and reliable standby generation, Hydro reported, according to Radio Canada. The utility said the turbine will have the ability to use renewable fuels once they become reliably available in the region.
Environmental assessment completed and board application filed
The environmental assessment was registered in March 2025 and released from further assessment in May 2025, subject to conditions outlined by the minister.

The utility submitted its Public Utilities Board application in March 2025, with an early works application approved the following month, Hydro reported.
Plant aims to replace aging Holyrood station
Because of problems with the 1,100-kilometre Labrador-Island Link transmission system, Hydro has said it will keep the current plant running until there is sufficient power generation. The consumer advocate pointed to the growing need for reliable energy on the Avalon Peninsula and cited the rolling blackouts experienced during DarkNL, a massive power outage in 2014 that kept tens of thousands in the dark for days.
Radio-Canada reported the regulator estimates the project is reasonable and necessary to ensure a reliable electricity supply at the least cost, while respecting the environment.
The Crown corporation did not obtain everything it had requested, the outlet noted.
Norwegian engineering firm Aker Solutions said on Nov. 20 it had been awarded a contract and given notice to proceed.
The company said work on the project will start immediately and is scheduled to be completed in 2030. The PUB wrote Friday’s approval only addresses the Avalon CT project; a proposed 154-megawatt unit at Bay d’Espoir, estimated at $1.08 billion, will be addressed separately.