Route 18 Closes Saturday in Potter Township for Bridge Demolition

Route 18 in Potter Township will close for a full day starting Saturday to demolish the old Frankfort Road Bridge over Raccoon Creek, PennDOT announced.

Saturday through 6 a.m. Saturday between PGT Way and Montgomery Dam Road, with a weather contingency extending it through 6 a.m. Monday, according to the PennDOT District 11 release. Raccoon Creek Road will also close at its intersection with Route 18 for the same period.

Detours route traffic onto I-376 and Route 68

Beaver County Radio published the posted detours, which differ by direction. Northbound Route 18 traffic will take Shippingport Hill Road to the Shippingport Bridge, then east on Route 68 to I-376 east toward Pittsburgh, exiting at Route 18 toward Monaca and Shippingport.

Southbound traffic will take I-376 west toward New Castle, exit at Route 68 west toward Midland, continue to Route 168 south toward Shippingport and Hookstown, cross the Shippingport Bridge, then turn left onto Shippingport Hill Road back to Route 18.

Drivers trying to reach Raccoon Creek Road from south of the closure are directed onto Bauer Road and Mowry Road. From the north, the detour follows the southbound Route 18 route to the Shippingport Bridge, then returns via Route 18 to Bauer and Mowry roads.

$25.27 million replacement nears finish

The prior bridge carried traffic while the new structure and a realigned roadway were built on the $25.27 million project, PennDOT said. Crews used a reduced-duration detour to complete the roadway tie-ins. The new bridge includes a sidewalk and aesthetic architectural surface treatments. Overall completion is expected in fall 2027.

The Pennsylvania Department of Transportation advises travelers to check conditions at 511PA.com or by dialing 5-1-1.